Granton.
The connection
we must not
leave behind.
Edinburgh is planning thousands of homes in Granton. The tram should be part of building that neighbourhood, not another promise pushed into the future.
CityScope opinion · Build the Granton tram. Take the route and delivery seriously. Stop treating the people who will depend on it as an afterthought.
The tram is part of the neighbourhood.
There is something backwards about planning a low-car neighbourhood and then treating its public transport connection as the optional bit.
Granton Waterfront has been planned around the assumption of a tram. It is part of how the neighbourhood is supposed to work. People need to get to work, get to college, reach appointments and get home again. They need a connection to the rest of Edinburgh that is more than a line on a masterplan.[1]
The officers’ recommendation going to committee on 10 September would put the southern extension first, with further work on the northern routes required. The Royal Infirmary and BioQuarter need better connections. So does Granton. The city should not need to turn that into a competition between the people who use them.[4]
Granton should not keep being the place Edinburgh will get round to later.
Build the homes. Build the connection.
council’s waterfront programme
214 social rent · 173 mid-market rent
The council’s waterfront programme proposes around 3,500 homes. Its first phase has planning permission for 847, including 214 for social rent and 173 for mid-market rent. That is a substantial new neighbourhood. It needs to function like one.[10][11]
It makes no sense to encourage people to live with fewer cars while leaving the transport that supports that choice permanently unresolved. A low-car neighbourhood needs more than low parking provision. It needs useful alternatives.
Granton already has residents, businesses and a community. They deserve better connections now. The new homes make the need to plan properly more urgent, not less.
For me, this comes down to what people can actually do from their front door. Which jobs can they reach? Can they get to college without the journey taking over their day? Can they visit friends, go out for dinner or get to an appointment without organising a lift?
The tram is not a substitute for schools, affordable housing or local services. It is part of the same job: building somewhere people can live well.
And success should mean the people already there get to share in it. Better connections should make Granton a better place to live, not just a more expensive place to buy.
Which homes, and when?
The figures cover the council’s waterfront programme and Phase One, not every development across north Edinburgh. They describe proposed homes, not completed homes. Phase One’s website still forecasts a start in early 2026 and completion in 2033; it does not confirm that construction has started.[11]
Their future homes are not there yet. Their future still counts.
This is the part of the debate I think Edinburgh is getting badly wrong.
The people who live along a proposed route can organise around it today. They know where they live, what they value and what they stand to lose. They can attend meetings, contact councillors and respond as residents of that place.
But who speaks for the person who will move into an affordable home in Granton in ten years? What about the teenager who will need to get to an apprenticeship? The person currently renting somewhere else who hopes to make their home here? The household that would rather not have the cost of a car built into every decision?
Their transport choices are being decided before they can speak as the residents who will have to live with them. That matters. Edinburgh is making decisions with consequences stretching well beyond the people who happen to be in the room today.
Young people and people building their working lives have a huge stake in this. A useful transport network affects where they can work, what they can study and how much independence they have. Those are not abstract benefits. They shape the choices available to someone starting out.
The same connection matters to someone getting to hospital, visiting family or staying involved in the city after retirement. This is about making everyday life easier, not deciding that one person’s time matters more than another’s. Disabled people, carers and people seeking work belong in that picture too.
Granton and District Community Council has already argued against deprioritising the northern extension, speaking up for both existing and future communities.[12]
Listening to current residents matters. Planning for future residents matters too. We cannot make the first group visible and treat the second as though they do not count yet.
A city has to plan for more people than the people who answered its latest consultation.
Whose voices, and whose journeys?
The community council’s letter expresses its position. The public consultation was self-selected; the council commissioned separate representative market research. My argument is that future residents deserve consideration too, rather than that either exercise tells us what they would choose.[12][4]
Useful access includes fares, safe crossings and the whole journey to the stop. The council’s preliminary Newhaven evaluation identifies limits for shift workers travelling outside typical hours. A connection has to work when people need it.[8]
Learn from the failure. Don’t stop building.
The original tram project was a mess. Edinburgh knows that. Businesses endured disruption, the city endured delays, and we got less than we were promised.
The airport–York Place line opened in May 2014, rather than the airport–Newhaven service originally expected in 2011. Lord Hardie’s inquiry identified failures in governance, design, procurement, reporting and risk management.[13][14]
That history matters. It should change how Edinburgh delivers major projects. But it cannot be the only part of the history we are willing to remember.
The later Newhaven extension opened to passengers on 7 June 2023. The council reported that it was delivered within its £207.3 million budget and scheduled completion window. Across the tram network, the operator recorded 12.5 million journeys in calendar 2025.[16][17][18]
To me, leaving Granton waiting again would be a failure on a par with the original build: another generation promised a connection and left without it. Edinburgh should pursue the whole north–south line, with Granton central to its delivery.
Waiting will not freeze today’s prices. The business case already models higher cash costs when construction spending falls in future years. Delaying Granton leaves the city exposed to further cost increases before shovels reach the ground, while residents go without the connection. Repeating that delay would be an expensive mistake.[6]
From the original promise to today2006 → 2026 +
- 2006–07
A wider network
Tram Acts and the original business case envisaged a wider system. Phase 1a linked the airport and Newhaven; Phase 1b would connect Haymarket and Granton Square.[13]
- 2009
Granton deferred
Financial constraints brought postponement of the Haymarket–Granton phase. This was a separate phase from the airport–Newhaven line that was itself later truncated.[15]
- May 2014
A shorter opening
Passenger services opened from the airport to York Place, after delay, cost escalation and reduction in scope.[14]
- June 2023
The line reaches Newhaven
Services began on 7 June. The council reported delivery within the £207.3m budget and scheduled completion window.[16][17]
- September 2023
The inquiry reports
Lord Hardie published findings and 24 recommendations. Governance, procurement, design and truthful reporting remain central lessons.[13]
- 2024–25
North–south planning returns
The February 2024 committee instructed consultation and market research for the strategic case. The 2025 consultation is now closed.[4][26]
- 10 September 2026
The next decision
Committee consideration of the strategic business case. At the checked date of this feature, officers’ recommendations await a decision.[3][4]
But there is a difference between learning from a failure and using it as a permanent reason never to build anything again.
The original project’s costs
The reported £776.7m cost of the truncated first line exceeded the £545m available budget for the larger airport–Newhaven first phase. The inquiry’s best estimate was £835.7m. These figures relate to the original project, not the later Newhaven extension.[14]
We should not have to lose it to see its value.
This summer, we got a very clear reminder of why the tram matters.
The fire at the former Debenhams building on Princes Street on 9 July interrupted the tram connection towards Leith and Newhaven. Work to make the damaged building safe kept the street closed. Normal services returned on 29 August.[19]
Buses still ran. People could still walk and cycle. But listen to the businesses describing what losing the tram did to their summer trade.
Argonaut Books
The owners · independent bookshop and café“It has undoubtedly had a profound negative impact on our trading this summer”
Malones Leith
Charlie Douglas · general manager“The trams being off has been a real blow for everyone down here”
Dulse
Dean Banks · owner“This closure has destroyed our trade in Leith!”
Lost in Leith
Paul Gibson · founder and managing director, Campervan Brewery“The closure of the trams in August resulted in a 26% reduction in our sales.”
These are the people running the bookshops, cafés, pubs and restaurants that make a neighbourhood worth visiting. They were telling us that the connection mattered to their trade.
That should be part of how we talk about transport investment. Not just tracks and vehicles, but customers arriving, friends meeting for a drink, someone browsing a bookshop and staying for a coffee.
Leith’s experience gives the Granton argument something concrete. A connection to the wider city is not just about getting residents out in the morning. It is also about bringing people in, making local businesses easier to reach and giving a neighbourhood a place in the life of Edinburgh.
We should not need to switch the trams off to admit that they matter.
The closure also exposed a weakness that needs fixing: the network needs another way through. Completing the loop from the city’s west end through Granton to Newhaven would provide a route around Princes Street, connecting the airport side of the network with Leith when the central route is blocked. That is another reason to build the Granton connection and plan for the waterfront link: expansion and resilience should go together.[4]
About these accounts and the closure
These statements describe the businesses’ own experience, not endorsements of the Granton extension or an area-wide sales average. They support an argument about access; they do not establish a numerical forecast for Granton’s future trade.
The incident was the former Debenhams fire, not the earlier Jenners fire. Section 4.27 of the September report recognises the resilience value of a Granton–Newhaven link (Line 1C) combined with the Granton–city centre connection. It prioritises the north–south corridor and leaves Line 1C for further work. The bypass described above depends on completing that loop; its waterfront section is not part of the current route shown on this map.[19][4]
There are real choices to make. Make them.
The plans retain walking and cycling through the Roseburn corridor alongside the tram. I think that needs to be much more prominent in this discussion, because it changes the argument quite considerably. We are not being asked to choose between having a tram and being able to walk or cycle through Roseburn. The proposal includes both.[9]
People can still object to how the corridor would change. But keeping it exactly as it is and retaining it as an active-travel route are two different things. Personally, I think using it to connect Granton to the tram network, while keeping walking and cycling, is a good use of that space.
Roseburn gives the tram a route separated from general traffic. The alternative through Orchard Brae takes it onto streets and across Dean Bridge, with the road-space and reliability issues that brings. For something people will depend on to get to work every day, that matters.[9][6]
There is also a substantial difference in cost. The early estimates for the northern extension are up to £800 million through Roseburn, compared with up to £1.2 billion through Orchard Brae, including risk allowances.[6]
The designs and transport choices
These remain candidate designs. A retained path can still be substantially changed, and replanting does not immediately replace mature trees. The assessment needs to show the actual walking, wheeling and cycling provision, accessibility and ecological effects.[9]
The strategic case argues that forecast growth requires greater capacity and an integrated network. That depends on housing and travel assumptions. Electric buses, bus priority, demand, service patterns and interchange need testing together. The tram will still need a strong bus network, with service patterns and journey times worked through as part of the design.[6]
Phasing the north–south route and examining South Suburban Railway proposals are compatible with taking Granton seriously. The southern extension’s passengers are not the problem to be solved.
Take the whole line forward.
The September business case puts an initial northern extension at up to £0.8 billion via Roseburn, or up to £1.2 billion via Orchard Brae, in early estimates at 2025/26 prices including risk and optimism bias.[6]
Those are serious sums. They need a serious funding and delivery plan.
They also need to be discussed accurately. The full north–south scheme is a different project scope, with early estimates of £2.49 billion via Roseburn or £2.91 billion via Orchard Brae, including continuation beyond the BioQuarter to Shawfair. Those figures are not the price of the Granton section alone.[6]
| Scheme scope | Estimate |
|---|---|
| North only · Roseburn | Up to £0.8bn |
| North only · Orchard Brae | Up to £1.2bn |
| South only · city centre–BioQuarter | Up to £1.7bn |
| Full scheme · via Roseburn | £2.49bn |
| Full scheme · via Orchard Brae | £2.91bn |
What the estimates include
The full-scheme table includes £970m of risk and optimism bias via Roseburn and £1.18bn via Orchard Brae. Base estimates include vehicles, development, land and complementary active-travel and interchange measures. Financing is separate. The report’s 25–40% higher outturn-cost scenario reflects spending in future years; it is not an agreed bill.[6]
Developing the outline business case is a separate cost: the committee report illustrates £36.6m for the full route, £23m for north only or £28m for south only. Phasing needs an account of shared work, interfaces and the later phase.[4]
The National Wealth Fund’s work is advisory, not a funding commitment. Potential income streams and borrowing capacity still need detailed testing. Fare revenue, operating performance, renewals, financing costs and accounting profit or loss are different measures. Covering operations would not repay the construction bill.[7][6]
The north–south tram is an investment in the Edinburgh we are building: new homes in Granton, better access to the Western General, and a stronger connection to the Royal Infirmary and BioQuarter. The business case gives the city a foundation to turn that ambition into a funded programme.
Edinburgh should take the whole line forward. Bringing the northern and southern sections through design and funding together would give Granton’s residents and future households a clear place in the programme from the start.
A coordinated programme can prepare utilities, organise construction and support local businesses as the route takes shape. Safe walking and cycling connections, accessible stops, affordable fares and coordinated buses should make the investment work for the whole journey.
That is the plan I support: a complete north–south connection, with a delivery team, funding plan and milestones that carry both ends towards construction. The city has built on its tram network before. It can do it again.
Construction can proceed in stages within that commitment. Each stage should bring the whole line closer, with Granton’s route and timetable built into the programme. Keep the work moving, secure the funding and get the line built.
Choose the route. Build the Granton tram.
The point is not to win an argument about trams. It is to make Edinburgh work better for the people who live here.
It is someone getting to work. A young person reaching college. A visit to a hospital, a café or a friend. It is being able to make a home in Granton without needing a car to reach the rest of the city.
Existing residents deserve that consideration. So do the people who will join them.
Edinburgh is deciding what kind of neighbourhood they will inherit before all of them have the chance to take part in the argument. That should make us more ambitious about their future, not more willing to put it off.
Choose the route. Put the funding and delivery plan together. Build the Granton tram.
Sources and evidence · 8 September 2026Read the sources. Make up your mind.
This is my case for building the Granton tram. These are the council papers, business accounts and other sources I have drawn on, with dates and notes so you can follow the argument for yourself.
About this map and its limitations
This is an embedded view of CityScope’s Edinburgh tram-map data, using the same MapLibre engine, OpenStreetMap background, network geometry, map controls and view-URL format. Operating tracks come from the existing OpenStreetMap dataset; candidate alignments come from the council consultation-map geometry already held by CityScope.
Only the current north–south corridor and its two northern alternatives are shown. Historical, safeguarded and speculative links are excluded. Inferred straight-line connectors are also excluded: gaps indicate missing source geometry, not planned breaks in the railway. The map is for understanding geography, not engineering or navigating a construction site.
Stops are indicative areas, including geocoded positions. Two misplaced legacy stop points have been omitted. Development outlines come from the CityScope summary dated 1 February 2026: they are contextual areas, not verified current construction status or legal boundaries. The Harbour and Lighthouse are separate projects; their homes are not included in this article’s waterfront total.
The historical disruption layer highlights existing track east of Princes Street. The Princes Street point is the existing tram stop, not the location or footprint of the fire. Services resumed on 29 August 2026.
Map data: © OpenStreetMap contributors (ODbL); council route material; CityScope’s existing development summary. Project images are credited in their development cards.
- Observed factWhy extend the tram network? ↗
City of Edinburgh Council · undated page
Future development and economic growth; bus integration · checked 2026-09-08 - Observed factLatest project updates ↗
City of Edinburgh Council · 2026-09-01
September 2026 update · checked 2026-09-08 - Decision stageTransport and Environment Committee agenda ↗
City of Edinburgh Council · 2026-09-10
Item 7.6 · checked 2026-09-08Agenda checked on 8 September. No item 7.6 party amendment or addendum was listed in the retrieved agenda. The meeting had not taken place.
- Officer recommendationGranton–BioQuarter strategic business case: committee report ↗
City of Edinburgh Council · 2026-09-10
Recommendations 1.1; §§4.26–4.27, 4.43–4.48 and 5–6 · checked 2026-09-08Report retrieved and read directly. Recommendations are not committee decisions.
- Officer recommendationAppendix 1: easy-read summary ↗
City of Edinburgh Council · 2026-09-10
Whole document · checked 2026-09-08 - Forecast / estimateAppendix 2: Strategic Business Case ↗
City of Edinburgh Council · 2026-08-14
§§2–4; §5.1–5.3, printed pp.65–69; Table 5.1, p.66 · checked 2026-09-08Report dated 14 August, published with the 10 September committee papers. Capital estimates include vehicles, development, land and complementary measures. §5.1.3 assumes Shawfair for full-scheme costing despite the shorter table headings. Financing is discussed separately; these are not lifetime debt-service totals.
- Advisory assessmentAppendix 3: National Wealth Fund advisory engagement ↗
National Wealth Fund / City of Edinburgh Council · 2026-09-10
Disclaimer, executive summary and funding workshops · checked 2026-09-08Exploratory funding work; not a funding commitment.
- Preliminary evaluationAppendix 4: initial tram benefits findings ↗
City of Edinburgh Council · 2026-09-10
Passenger experience; access to jobs; conclusion · checked 2026-09-08User survey and stakeholder evidence. Notes limits for shift workers. Final benefits report is scheduled for November 2026.
- Candidate designGranton to the city centre: route options ↗
City of Edinburgh Council · undated page
Roseburn and Orchard Brae sections · checked 2026-09-08Consultation-stage designs, subject to further assessment. No final engineering dimensions are claimed here.
- Programme proposalGranton Waterfront programme ↗
City of Edinburgh Council · undated page
Programme aims and proposed homes · checked 2026-09-08 - Programme proposalGranton Waterfront: Phase One ↗
Granton Waterfront / City of Edinburgh Council · undated page
Homes, tenures, permission and programme · checked 2026-09-08Page still forecasts an early-2026 construction start and 2033 completion. It does not establish the actual start on site; this feature does not claim it has occurred.
- Stakeholder positionTrams to/from Granton: statement to TEC ↗
Granton and District Community Council · 2026-09-04
Open letter following the 31 August meeting · checked 2026-09-08 - Inquiry findingEdinburgh Tram Inquiry report ↗
Lord Hardie / Edinburgh Tram Inquiry · 2023-09-19
Executive summary; chapters 1–2; recommendations · checked 2026-09-08 - Reported inquiry findingInquiry findings and project costs ↗
Scottish Legal News · 2023-09-19
Original budget, truncated opening and costs · checked 2026-09-08 - Historical accountEdinburgh tram news archive: 2009 ↗
Light Rail Transit Association · 2009
Postponement of Line 1b · checked 2026-09-08 - Observed factNewhaven passenger launch announcement ↗
City of Edinburgh Council · 2023-05-25
Budget and scheduled delivery statement · checked 2026-09-08 - Observed factTrams to Newhaven ↗
Edinburgh Trams · undated page
Passenger services began 7 June 2023 · checked 2026-09-08 - Observed fact2025: A Year on Track ↗
Edinburgh Trams · 2026-01-12
12.5 million customer journeys during calendar 2025 · checked 2026-09-08 - Observed factPrinces Street reopens ↗
City of Edinburgh Council · 2026-08-29
Fire location, safety works and restoration of services · checked 2026-09-08 - Historical service disruptionTram disruption: Princes Street closure ↗
Edinburgh Trams · 2026-07
Historical service notice · checked 2026-09-08Historical context only. Normal service resumed on 29 August.
- Business testimonyArgonaut Books sales statement ↗
The Edinburgh Minute · 2026-08-26
Argonaut Books item and linked Instagram post · checked 2026-09-08Original Instagram data could not be retrieved. The comparison period behind the reported 35% fall is not asserted.
- Observed factArgonaut Books café ↗
Argonaut Books · undated page
Café information · checked 2026-09-08 - Business testimonyLeith venues adapt to tram suspension ↗
Scottish Licensed Trade News · 2026-07-30
Charlie Douglas, Malones Leith · checked 2026-09-08 - Business testimonyDean Banks on the Leith closure ↗
The Edinburgh Minute · 2026-07-28
Reproduced public post dated 27 July · checked 2026-09-08 - Business testimonyLost in Leith closure announcement ↗
The Edinburgh Minute · 2026-09-07
Paul Gibson statement and consolidation context · checked 2026-09-08 - Consultation recordNorth–south tram consultation ↗
City of Edinburgh Council · 2025
Closed consultation · checked 2026-09-08 - Project proposalThe Art Works and National Collections Hub ↗
National Galleries of Scotland · undated page
Project scope and partnership with National Museums Scotland · checked 2026-09-08 - Existing institutionNational Museums Collection Centre ↗
National Museums Scotland · undated page
Collections, research, conservation, address and guided tours · checked 2026-09-08 - Developer accountFormer Granton car factory to become mid-market homes ↗
Lar Housing Trust · undated page
Approved 28-townhouse conversion · checked 2026-09-08 - Project proposal20 West Shore Road creative and community hub ↗
City of Edinburgh Council · undated page
Edinburgh Palette project description · checked 2026-09-08 - Programme proposalSilverlea homes ↗
Granton Waterfront / City of Edinburgh Council · undated page
143 homes, football facilities and pedestrian improvements · checked 2026-09-08Newer figure differs from the 142-home historic planning snapshot. Availability in 2026 is a forecast.
- Dated construction updateResidents give thumbs up to Granton Waterfront ↗
City of Edinburgh Council · 2026-05-13
Silverlea work underway and 143-home programme · checked 2026-09-08 - Completed public spaceNew park opens within former Granton gasholder ↗
City of Edinburgh Council · 2025-04
Public park opening · checked 2026-09-08 - Completed regeneration projectGranton Waterfront project timeline ↗
Granton Waterfront / City of Edinburgh Council · undated page
March 2023: Granton Station Creative Works opens · checked 2026-09-08
CityScope opinion. Sources up to date as of 8 September 2026