Western General Hospital 55 Crewe Road South Edinburgh EH4 2XU

Application GrantedMechanical Plant, Flues & Ventilation
Planning document
1 / 5
Received

5 September 2025

Validated

12 September 2025

Planning Signals

2 detected traits

Use
Health Care
Specific
Mechanical Plant
Application Insights

No form insights available yet.

AI summary

Pair of generators on new concrete plinths proposed at IGC North and South blocks, boosting emergency power with minimal building change. .

Impact scale

Estimated scale of impact on the surrounding area.

3/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application EDI/25/04628/FUL

Western General Hospital 55 Crewe Road South Edinburgh EH4 2XU

Application GrantedMechanical Plant, Flues & VentilationReceived Local authority

Pair of generators on new concrete plinths proposed at IGC North and South blocks, boosting emergency power with minimal building change. .

Reference
EDI/25/04628/FUL
Address
Western General Hospital 55 Crewe Road South Edinburgh EH4 2XU
Status
Application Granted
Category
Mechanical Plant, Flues & Ventilation
Impact scale
3/10
Authority
Local authority
Received
Validated
Last scraped
Record created
Latitude
55.9623266
Longitude
-3.2350851

Plain-language summary

Pair of generators on new concrete plinths proposed at IGC North and South blocks, boosting emergency power with minimal building change. .

As filed with the council

Proposal is to install x2 generators, one at the IGC North building and one at the IGC South Building.