Overview
- Today
- The site is used as a data centre. Existing external equipment includes a backup generator, tank, base and condenser cages, alongside a small bottle store.
- Proposed
- Remove the existing equipment and bottle store. Add a secure fenced plant compound with backup power plant, fuel tank and condensers, an electric vehicle charger and façade louvres.
- Size
- 1,317 m² site area
- Stage
- Decided on 4 Feb 2026: Granted.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application proposes technical upgrades at a data centre at Unit 4–5, 13 South Gyle Crescent. It includes removing existing external power and cooling equipment and a small bottle store, then installing a fenced plant compound, backup power plant, fuel tank, condensers and an electric vehicle charger. New louvres—slatted panels—are proposed on the building façade. The application does not include new homes or non-residential floorspace.
Written with AI from the application form and the council record.
Keep reading
Track this application
How do I track planning application EDI/25/06284/FUL?
Follow it on City Scope. This page is checked against the City of Edinburgh Council planning register and shows the latest status, decision and documents for EDI/25/06284/FUL. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the City of Edinburgh Council planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
The existing external backup generator, tank and base would be removed.
- 02
Existing condenser cages and a small single-storey blockwork bottle store would be removed.
- 03
A new secure fenced plant compound would be added in the service yard, with backup power plant, a fuel tank and condensers.
- 04
A new electric vehicle charger and louvres on the building façade are proposed.
Questions
Has work started?
No. The form says the work has not started or been completed.
Would vehicle access change?
The form says no new or altered vehicle access to or from a public road is proposed.
From the application form
The application form
Every answer the applicant gave on the council’s form, searchable.
Tags
- Facade / Exterior
- EV Charging
- External Alterations
- Fuel Tank
- Generator
- Mechanical Plant
- Plant Enclosure
- Secure Compound
What each tag is based on
- Facade / Exterior
- “Upgrade New secure fenced plant compound to service yard to include new back up power plant, fuel tank and condensers. New EV charger. New louvres to building facade.”
- EV Charging
- “"New EV charger"”
- External Alterations
- “"New louvres to building facade"”
- Fuel Tank
- “"include new back up power plant, fuel tank and condensers"”
- Generator
- “"back up power plant"”, “"backup generator"”
- Mechanical Plant
- “category":"Mechanical Plant, Flues & Ventilation"”, “"new back up power plant, fuel tank and condensers"”
- Plant Enclosure
- “"New secure fenced plant compound"”
- Secure Compound
- “"New secure fenced plant compound"”, “"service yard"”
All documents (5)
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
The council has decided on 4 February 2026.
- Received1 Dec 2025
- Validated1 Dec 2025The council has everything it needs.
- Comments closed22 Dec 2025Usual deadline. Late comments may still count.
- Target decision1 Feb 20262-month target for local developments.
- Decision4 Feb 2026Granted.
Planning terms
- Full planning permission
- Permission for the actual building work or change of use, as drawn. The standard type of planning application.
The record
- Reference
- EDI/25/06284/FUL
- Address
- Unit 4 - 5, 13 South Gyle Crescent Edinburgh EH12 9EB
- Status
- Application Granted
- Council decision
- Granted
- Decision issued
- Category
- Mechanical Plant, Flues & Ventilation
- Impact scale
- 5/10
- Authority
- The City of Edinburgh Council
- Received
- Validated
- Last checked
- Added to City Scope
- Ward
- Drum Brae/Gyle
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.