Planning applicationABS/APP/2026/0071

Netherton Hub Land West Of Parkhills Farm Blackhills Peterhead

DecidedWorth watchingLegal / Administrative
Official records · coverage in progress

1,742 of 1,898 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 156 records from that period are still being added or checked.

Proposals and decisions come from Aberdeenshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

16 January 2026

Validated

21 January 2026

Planning Signals

5 detected traits

Works
Landscaping
Specific
ArchaeologyCondition DischargeEcologySubstation
AI summary

Proposed discharge of conditions for Netherton strategic electricity transmission huboffsite landscaping, PMO, ECoW, BEMP and archaeology details.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ABS/APP/2026/0071

Netherton Hub Land West Of Parkhills Farm Blackhills Peterhead

DecidedLegal / AdministrativeReceived Aberdeenshire Council

Proposed discharge of conditions for Netherton strategic electricity transmission huboffsite landscaping, PMO, ECoW, BEMP and archaeology details.

Reference
ABS/APP/2026/0071
Address
Netherton Hub Land West Of Parkhills Farm Blackhills Peterhead
Status
Decided
Category
Legal / Administrative
Impact scale
7/10
Authority
Aberdeenshire Council
Received
Validated
Last scraped
Record created

Plain-language summary

Proposed discharge of conditions for Netherton strategic electricity transmission huboffsite landscaping, PMO, ECoW, BEMP and archaeology details.

As filed with the council

Discharge of Planning Conditions 5 (Offsite Landscaping), 6 (PMO), 9 (ECoW), 10 (BEMP) and 11 (Archaeology) of Planning Permission Reference APP/2024/1714 for National for Erection of a Strategic Electricity Transmission Hub Including 400kV AC Substation, 132kV AC Substation, 2 HVDC Converter Stations, Transmission Hall, Spares Warehouse, Operations Base and Associated Works