Planning application · ABS/APP/2026/0804
Certificate confirms start of approved 45MW battery scheme near Fraserburgh.
Land East Of A981 Fraserburgh Aberdeenshire
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- Legal / Administrative
- Minor 1/10
- Access Controlled Security Fencing
- Associated Infrastructure
- Battery Storage
- Cctv Installation
- Condition Compliance
Overview
- Today
- Topsoil stripped; foundation excavated and concrete blinding laid
- Proposed
- Confirmation that these works began the approved development
- Size
- 45 MW approved scheme capacity
- Stage
- Decided on 15 Jun 2026: Approved.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
This application sought confirmation that work had begun on the battery energy storage scheme approved under APP/2023/0193. The form says topsoil was stripped and a foundation excavated, with concrete blinding laid, on 10 April 2026. Aberdeenshire Council approved the application.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
1,742 of 1,898 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 156 records from that period are still being added or checked.
Proposals and decisions come from Aberdeenshire Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application ABS/APP/2026/0804?
Follow it on City Scope. This page is checked against the Aberdeenshire Council planning register and shows the latest status, decision and documents for ABS/APP/2026/0804. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the Aberdeenshire Council planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
The approved scheme includes substations, security fencing, CCTV, a vehicle access and associated infrastructure.
Questions
What does this application relate to?
It relates to the existing permission APP/2023/0193 for a battery energy storage system compound. It sought confirmation that work had started under that permission.
What work had taken place?
The form says topsoil had been stripped to a depth of 500mm and a foundation excavated, with concrete blinding laid at its base.
From the application form
The application form
Every answer the applicant gave on the council’s form, searchable.
Tags
- Access Controlled Security Fencing
- Associated Infrastructure
- Battery Storage
- Cctv Installation
- Condition Compliance
- Industrial Logistics
- Parking Access
- Substation
What each tag is based on
- Access Controlled Security Fencing
- “Erection of Security Fencing”
- Associated Infrastructure
- “Associated Infrastructure”
- Battery Storage
- “45MW Battery Energy Storage System Compound”
- Cctv Installation
- “CCTV”
- Condition Compliance
- “Confirmation Existing Planning Permission”
- Industrial Logistics
- “battery storage compound”
- Parking Access
- “Formation of Vehicular Access”
- Substation
- “Siting of Substations”
As lodged
The drawings.
All documents (3)
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
The council has decided on 15 June 2026.
- Received13 May 2026
- Validated19 May 2026The council has everything it needs.
- Comments closed9 Jun 2026Usual deadline. Late comments may still count.
- Target decision19 Jul 20262-month target for local developments.
- Decision15 Jun 2026Approved.
The record
- Reference
- ABS/APP/2026/0804
- Address
- Land East Of A981 Fraserburgh Aberdeenshire
- Status
- Decided
- Council decision
- Approved
- Decision issued
- Category
- Legal / Administrative
- Impact scale
- 1/10
- Authority
- Aberdeenshire Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.