Planning applicationABS/ENQ/2026/0739

Aspen Offshore Wind Farm (Onshore Infrastructure) Land At Craig Stirling North, North East And North West Of Newtonhill Connecting To Fetteresso Forest Aberdeenshire

DecidedWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

1,742 of 1,898 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 156 records from that period are still being added or checked.

Proposals and decisions come from Aberdeenshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

30 April 2026

Validated

30 April 2026

Planning Signals

4 detected traits

Specific
Associated InfrastructureOffshore Wind FarmSubstationUnderground Electrical Cabling
Application Insights

No form insights available yet.

AI summary

Plans for Aspen offshore wind grid connection: electrical cables, a new substation and associated infrastructure at Stirling/North West Newt. onshore route.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ABS/ENQ/2026/0739

Aspen Offshore Wind Farm (Onshore Infrastructure) Land At Craig Stirling North, North East And North West Of Newtonhill Connecting To Fetteresso Forest Aberdeenshire

DecidedRenewable Energy, EV & Heat PumpsReceived Aberdeenshire Council

Plans for Aspen offshore wind grid connection: electrical cables, a new substation and associated infrastructure at Stirling/North West Newt. onshore route.

Reference
ABS/ENQ/2026/0739
Address
Aspen Offshore Wind Farm (Onshore Infrastructure) Land At Craig Stirling North, North East And North West Of Newtonhill Connecting To Fetteresso Forest Aberdeenshire
Status
Decided
Category
Renewable Energy, EV & Heat Pumps
Impact scale
8/10
Authority
Aberdeenshire Council
Received
Validated
Last scraped
Record created
Latitude
56.9979
Longitude
-2.2109

Plain-language summary

Plans for Aspen offshore wind grid connection: electrical cables, a new substation and associated infrastructure at Stirling/North West Newt. onshore route.

As filed with the council

Onshore Transmission Infrastructure for Aspen Offshore Wind Farm Including Installation of Electrical Cables, Erection of Substation and Associated Infrastructure to Connect to the National Electricity Transmission System