Planning applicationAGB/26/00395/SCREEN

Dunoon Electricity Sub Station Sandbank Argyll And Bute

UnknownNew-Build & Major Development
Official records · coverage in progress

1,438 of 1,612 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 174 records from that period are still being added or checked.

Proposals and decisions come from Argyll and Bute Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

27 February 2026

Validated

27 February 2026

Planning Signals

2 detected traits

Specific
Eia ScreeningSubstation
AI summary

EIA screening opinion for replacing the Dunoon electricity substation at Sandbank, with new grid-supply equipment and associated cabling.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application AGB/26/00395/SCREEN

Dunoon Electricity Sub Station Sandbank Argyll And Bute

UnknownNew-Build & Major DevelopmentReceived Argyll and Bute Council

EIA screening opinion for replacing the Dunoon electricity substation at Sandbank, with new grid-supply equipment and associated cabling.

Reference
AGB/26/00395/SCREEN
Address
Dunoon Electricity Sub Station Sandbank Argyll And Bute
Status
Unknown
Category
New-Build & Major Development
Impact scale
7/10
Authority
Argyll and Bute Council
Received
Validated
Last scraped
Record created
Latitude
55.9758
Longitude
-4.9479

Plain-language summary

EIA screening opinion for replacing the Dunoon electricity substation at Sandbank, with new grid-supply equipment and associated cabling.

As filed with the council

Screening opinion for replacement substation