Planning applicationANG/25/00582/MSC

Well House Airlie

Approved Subject to ConditionsNew-Build & Major Development
Official records · coverage in progress

438 of 559 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 121 records from that period are still being added or checked.

Proposals and decisions come from Angus Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

28 October 2025

Validated

5 November 2025

Planning Signals

5 detected traits

Works
Boundary TreatmentLandscaping
Specific
Drainage Wastewater InfrastructureMatters Specified In ConditionsParking Access
Application Insights

No form insights available yet.

AI summary

Reserved matters for building(s) including siting/design, site layout and access, boundaries, landscaping, ground levels and foul/surface drainage.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ANG/25/00582/MSC

Well House Airlie

Approved Subject to ConditionsNew-Build & Major DevelopmentReceived Angus Council

Reserved matters for building(s) including siting/design, site layout and access, boundaries, landscaping, ground levels and foul/surface drainage.

Reference
ANG/25/00582/MSC
Address
Well House Airlie
Status
Approved Subject to Conditions
Category
New-Build & Major Development
Impact scale
6/10
Authority
Angus Council
Received
Validated
Last scraped
Record created
Latitude
56.6361
Longitude
-3.1416

Plain-language summary

Reserved matters for building(s) including siting/design, site layout and access, boundaries, landscaping, ground levels and foul/surface drainage.

As filed with the council

Approval of matters specified in condition 3 (a), (b), (c), (d) and (e) of planning application 22/00515/PPPL including the siting, design and external appearance of the building(s); layout of the site; the means of access; the boundary enclosures and a scheme of hard and soft landscaping; the existing and proposed ground levels and finished floor levels; and the means of surface water and foul drainage arrangements