Planning application · ANG/26/00200/EIASCR

ANG/26/00200/EIASCREIA Not Required

Berwick Bank wind farm consent variation covers monopiles and an export cable.

Berwick Bank Offshore Wind Farm

Angus Council

Free with a City Scope account. One email, when the council decides.

Also email me new applications in this council · £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
Renewable Energy, EV & Heat Pumps
Scale
Large 7/10
Tags
  • Offshore Foundations And Export Cables
  • Offshore Wind Farm
  • Section 36 Consent

Overview

Proposed
A variation concerning monopiles and an additional export cable.
Type
Environmental impact screening
Stage
Past its target date of 31 May 2026.

The council writes only to properties within 20 metres of an application site. Who is told

In plain English

This is a consultation about a variation to the existing Section 36 consent for Berwick Bank Wind Farm. It concerns monopiles and an additional export cable. The record says an environmental impact assessment is not required.

Written with AI from the application form and the council record.

Keep reading

Official records · coverage in progress

438 of 559 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 121 records from that period are still being added or checked.

Proposals and decisions come from Angus Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register

Track this application

How do I track planning application ANG/26/00200/EIASCR?

Follow it on City Scope. This page is checked against the Angus Council planning register and shows the latest status, decision and documents for ANG/26/00200/EIASCR. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the Angus Council planning portal.

Set up a planning alert