Planning applicationANG/26/00460/EIASCR

Cable Route From Lunanhead To Montreathmont Montreathmont Forfar

Awaiting decisionNew-Build & Major Development
Official records · coverage in progress

438 of 559 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 121 records from that period are still being added or checked.

Proposals and decisions come from Angus Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

6 August 2026

Validated

6 August 2026

AI summary

Proposed 12.8km underground cable linking consented solar farm and BESS to Lunanhead substation.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ANG/26/00460/EIASCR

Cable Route From Lunanhead To Montreathmont Montreathmont Forfar

Awaiting decisionNew-Build & Major DevelopmentReceived Angus Council

Proposed 12.8km underground cable linking consented solar farm and BESS to Lunanhead substation.

Reference
ANG/26/00460/EIASCR
Address
Cable Route From Lunanhead To Montreathmont Montreathmont Forfar
Status
Awaiting decision
Category
New-Build & Major Development
Impact scale
7/10
Authority
Angus Council
Received
Validated
Last scraped
Record created
Latitude
56.6688
Longitude
-2.6747

Plain-language summary

Proposed 12.8km underground cable linking consented solar farm and BESS to Lunanhead substation.

As filed with the council

Underground cable route to connect the consented solar farm and BESS development at Montreathmont (Angus Council ref: 22/00460/FULM) to the point of connection (PoC) at Lunanhead substation. The length of the cable will be approximately 12.8 kilometres.