Planning application · BARNET/TCP/0266/26
Proposed like-for-like replacement of about 0.77km of underground water mains, mostly open-cut, within and near a nature conservation site.
Hampstead Way, Reynolds Close and Hampstead Heath Extension London NW11 7DY
- Parking, Access & Highways
- Medium 6/10
- Civil Works
- Utility Connection
Overview
Why it’s worth watching
Replacement of roughly 0.77km of high-risk water mains through and beside a Site of Metropolitan Importance for Nature Conservation is a material infrastructure change with local disruption implications.
- Stage
- Past its target date of 3 Jul 2026.
As lodged with the council
Instalation of replacement high pressure main water pipe along Hampstead Way, Reynolds Close and Hampstead Heath Extension between Wellgarth Road and Wildwood Road NW11 7XX. Works to be carried out are a like-for-like replacement of existing distribution mains in Hampstead Way and Hampstead Heath DMA. Works consist of replacement of approximately 0.77km of an existing cast iron/ spun iron/ steel mains with a 180mm, 150mm and 125mm polyethylene (PE) pipeline which runs within and adjacent to Hampstead Heath Site of Metropolitan Importance for Nature Conservation (SINC). The mains to be replaced are entirely below-ground and the default construction method will be open-cut with excavations at 900mm depth and 480mm width to safely access and replace the pipe. There may be potential for the works to be carried out using trenchless techniques (slip-lining and/or directional drilling methodology). Thames Water has identified these assets as being at high risk of failure due to recurring bursts along the route.
The headline is a plain-English summary written with AI from the council record.
Keep reading
Track this application
How do I track planning application BARNET/TCP/0266/26?
Follow it on City Scope. This page is checked against the Barnet planning register and shows the latest status, decision and documents for BARNET/TCP/0266/26. To comment on the application, use the Barnet planning portal.
The impact
What it involves.
Tags
- Civil Works
- Utility Connection
What each tag is based on
- Civil Works
- “Works consist of replacement of approximately 0.77km of an existing cast iron/ spun iron/ steel mains with a 180mm, 150mm and 125mm polyethylene (PE) pipeline”, “default construction method will be open-cut with excavations at 900mm depth and 480mm width”
- Utility Connection
- “replacement of existing distribution mains”
Where it’s at
Comments have closed. The target date for a decision has passed.
- Received8 May 2026
- Validated8 May 2026The council has everything it needs.
- Comments closed29 May 2026Usual deadline. Late comments may still count.
- Target decision (next)3 Jul 20268-week target for minor and other applications.
- DecisionNot yet
The record
- Reference
- BARNET/TCP/0266/26
- Address
- Hampstead Way, Reynolds Close And Hampstead Heath Extension London NW11 7DY
- Status
- Unknown
- Category
- Parking, Access & Highways
- Impact scale
- 6/10
- Authority
- Barnet
- Received
- Validated
- Last checked
- Added to City Scope
- Ward
- Garden Suburb
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.