Planning applicationDGY/25/2054/CSG

Proposed Hartsgarth Wind Farm Langholm Moor

DecidedWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

1,479 of 1,663 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 184 records from that period are still being added or checked.

Proposals and decisions come from Dumfries and Galloway Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

6 November 2025

Validated

6 November 2025

Planning Signals

3 detected traits

Specific
Associated InfrastructureEia ScopingWind Turbine
AI summary

Scoping for a large wind farm, up to 18 turbines (max 220m tip height) with associated infrastructure and grid connection works.

Impact scale

Estimated scale of impact on the surrounding area.

9/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application DGY/25/2054/CSG

Proposed Hartsgarth Wind Farm Langholm Moor

DecidedRenewable Energy, EV & Heat PumpsReceived Dumfries and Galloway Council

Scoping for a large wind farm, up to 18 turbines (max 220m tip height) with associated infrastructure and grid connection works.

Reference
DGY/25/2054/CSG
Address
Proposed Hartsgarth Wind Farm Langholm Moor
Status
Decided
Category
Renewable Energy, EV & Heat Pumps
Impact scale
9/10
Authority
Dumfries and Galloway Council
Received
Validated
Last scraped
Record created

Plain-language summary

Scoping for a large wind farm, up to 18 turbines (max 220m tip height) with associated infrastructure and grid connection works.

As filed with the council

CONSULTATION REQUEST FROM SCOTTISH GOVERNMENT IN RELATION TO SCOPING OPINION UNDER THE TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND) REGULATIONS 2017 FOR PROPOSED WIND FARM COMPRISING UP TO 18 WIND TURBINES (MAXIMUM TIP HEIGHT 220 METRES) AND ASSOCIATED INFRASTRUCTURE