Planning applicationDGY/26/0464/SCO

Land To The North Of The Former Chapelcross Nuclear Power Station, Near Annan

DecidedWorth watchingNew-Build & Major Development
Official records · coverage in progress

1,479 of 1,663 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 184 records from that period are still being added or checked.

Proposals and decisions come from Dumfries and Galloway Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

20 March 2026

Validated

25 March 2026

Planning Signals

5 detected traits

Specific
Data CentreEia ScopingSubstationSwitch RoomTraining And Innovation Centres
AI summary

Scoping opinion sought for a data-centre-led complex with multiple new buildings and a power substation/switch room at Chapelcross.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application DGY/26/0464/SCO

Land To The North Of The Former Chapelcross Nuclear Power Station, Near Annan

DecidedNew-Build & Major DevelopmentReceived Dumfries and Galloway Council

Scoping opinion sought for a data-centre-led complex with multiple new buildings and a power substation/switch room at Chapelcross.

Reference
DGY/26/0464/SCO
Address
Land To The North Of The Former Chapelcross Nuclear Power Station, Near Annan
Status
Decided
Category
New-Build & Major Development
Impact scale
8/10
Authority
Dumfries and Galloway Council
Received
Validated
Last scraped
Record created

Plain-language summary

Scoping opinion sought for a data-centre-led complex with multiple new buildings and a power substation/switch room at Chapelcross.

As filed with the council

REQUEST FOR SCOPING OPINION UNDER THE TOWN AND COUNTRY PLANNING ENVIRONMENTAL IMPACT ASSESSMENT (SCOTLAND) REGULATIONS 2017 FOR A PROPOSED DATA-CENTRE LED DEVELOPMENT COMPRISING ERECTION OF BUILDINGS TO BE USED AS DATA CENTRES, TRAINING CENTRE/RECEPTION/SECURITY BUILDINGS, GENERAL INDUSTRIAL BUILDINGS, AND FORMATION OF SUBSTATION INCLUDING SWITCH ROOM BUILDING AND ASSOCIATED POWER DISTRIBUTION AND ELECTRICAL INFRASTRUCTURE