Planning applicationDGY/26/0605/SCR

Craig Whithorn Newton Stewart DG8 8DG

Assessment StageWorth watchingNew-Build & Major Development
Official records · coverage in progress

1,479 of 1,663 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 184 records from that period are still being added or checked.

Proposals and decisions come from Dumfries and Galloway Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 2
Received

13 April 2026

Validated

13 April 2026

Planning Signals

8 detected traits

Specific
Egg Production UnitEgg Production Unit 28000 BirdsEia ScreeningFeed SiloRetrospectiveSeptic Tank
Application Insights

No form insights available yet.

AI summary

Screening opinion for 5 egg production units with feed silos, staff welfare building, access track, parking and septic works (partly retrospective).

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application DGY/26/0605/SCR

Craig Whithorn Newton Stewart DG8 8DG

Assessment StageNew-Build & Major DevelopmentReceived Dumfries and Galloway Council

Screening opinion for 5 egg production units with feed silos, staff welfare building, access track, parking and septic works (partly retrospective).

Reference
DGY/26/0605/SCR
Address
Craig Whithorn Newton Stewart DG8 8DG
Status
Assessment Stage
Category
New-Build & Major Development
Impact scale
7/10
Authority
Dumfries and Galloway Council
Received
Validated
Last scraped
Record created
Latitude
54.747214
Longitude
-4.463889

Plain-language summary

Screening opinion for 5 egg production units with feed silos, staff welfare building, access track, parking and septic works (partly retrospective).

As filed with the council

REQUEST FOR SCREENING OPINION UNDER THE TOWN AND COUNTRY PLANNING ENVIRONMENTAL IMPACT ASSESSMENT (SCOTLAND) REGULATIONS 2017 FOR ERECTION OF 5 EGG PRODUCTION UNITS (28,000 BIRDS), SITING OF 2 FEED SILOS, STAFF WELFARE UNIT AND BIO-SECURITY CONTAINER, FORMATION OF ACCESS TRACK, PARKING AND TURNING, INSTALLATION OF SEPTIC TANK AND SOAKAWAY, ENGINEERING OPERATIONS AND ASSOCIATED WORKS - PARTIALLY RETROSPECTIVE