Planning application · DGY/26/1077/CSG
132kV overhead line on wooden poles proposed near Langholm.
Proposed Callisterhall Wind Farm Connection Langholm
Free with a City Scope account. One email, when the council decides.
Also email me new applications in this council · £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- Renewable Energy, EV & Heat Pumps
- Medium 6/10
- Eia Scoping
- Overhead Utility Lines
- Section 36 Consent
- Wooden Pole
Overview
Why it’s worth watching
A scoping consultation for a 132kV overhead line connecting the proposed Callisterhall Wind Farm, a major energy infrastructure proposal with clear regional public significance.
- Proposed
- A new 132kV overhead line supported on wooden poles
- Size
- 132 kV line voltage
- Stage
- Past its target date of 19 Aug 2026.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The Scottish Government has asked for a scoping opinion about a proposed 132kV overhead line supported on wooden poles. A scoping opinion sets out what environmental effects should be assessed in an environmental impact assessment. This is a consultation about the assessment’s scope, not a decision on permission.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
1,479 of 1,663 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 184 records from that period are still being added or checked.
Proposals and decisions come from Dumfries and Galloway Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application DGY/26/1077/CSG?
Follow it on City Scope. This page is checked against the Dumfries and Galloway Council planning register and shows the latest status, decision and documents for DGY/26/1077/CSG. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the Dumfries and Galloway Council planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
A new overhead line supported on wooden poles is proposed. The route is not given.
Questions
Is this an application for permission to build the line?
The record describes a request for a scoping opinion, not a decision on permission.
Tags
- Eia Scoping
- Overhead Utility Lines
- Section 36 Consent
- Wooden Pole
What each tag is based on
- Eia Scoping
- “SCOPING OPINION UNDER THE TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND) REGULATIONS 2017”
- Overhead Utility Lines
- “CONSTRUCTION AND OPERATION OF A NEW 132KV OVERHEAD LINE (OHL) SUPPORTED ON WOODEN POLES”
- Section 36 Consent
- “CONSULTATION REQUEST FROM SCOTTISH GOVERNMENT IN RELATION TO SCOPING OPINION UNDER THE TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) (SCOTLAND) REGULATIONS 2017”
- Wooden Pole
- “NEW 132KV OVERHEAD LINE (OHL) SUPPORTED ON WOODEN POLES”
As lodged
The drawings.
Where it’s at
Comments have closed. The target date for a decision has passed.
- Received19 Jun 2026
- Validated19 Jun 2026The council has everything it needs.
- Comments closed10 Jul 2026Usual deadline. Late comments may still count.
- Target decision (next)19 Aug 20262-month target for local developments.
- DecisionNot yet
The record
- Reference
- DGY/26/1077/CSG
- Address
- Proposed Callisterhall Wind Farm Connection Langholm
- Status
- Assessment Stage
- Category
- Renewable Energy, EV & Heat Pumps
- Impact scale
- 6/10
- Authority
- Dumfries and Galloway Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.