Planning applicationDND/26/0015/NMV

1 Portree Avenue Broughty Ferry Dundee DD5 3EG

RegisteredWindows, Doors & Glazing
Official records · coverage in progress

717 of 718 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 1 records from that period are still being added or checked.

Proposals and decisions come from Dundee City Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 3
Received

9 June 2026

Validated

9 June 2026

Planning Signals

9 detected traits

Works
Roof WorksInternal Alterations
Specific
Bi Fold DoorsConservatory RemovalDoor OpeningKitchen Diner
Application Insights

No form insights available yet.

AI summary

Minor rework to kitchen and roof drainage: sink/hob changes, boiler and SVP redirected, plus conservatory door added and one south window removed.

Impact scale

Estimated scale of impact on the surrounding area.

4/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application DND/26/0015/NMV

1 Portree Avenue Broughty Ferry Dundee DD5 3EG

RegisteredWindows, Doors & GlazingReceived Dundee City Council

Minor rework to kitchen and roof drainage: sink/hob changes, boiler and SVP redirected, plus conservatory door added and one south window removed.

Reference
DND/26/0015/NMV
Address
1 Portree Avenue Broughty Ferry Dundee DD5 3EG
Status
Registered
Category
Windows, Doors & Glazing
Impact scale
4/10
Authority
Dundee City Council
Received
Validated
Last scraped
Record created
Latitude
56.4739
Longitude
-2.8649

Plain-language summary

Minor rework to kitchen and roof drainage: sink/hob changes, boiler and SVP redirected, plus conservatory door added and one south window removed.

As filed with the council

EX-26-A , Existing Block Plan Existing SVP added to roof area. EX-27-A , Existing Floor Plans Sink added and hob relocated within the kitchen on the ground floor plan. EX-28-A , Existing Elevations Conservatory door added to south elevation. SVP added to all relevant elevations. Extract terminal for first floor shower room added to south elevation. EX-29-A , Existing Roof Plan Existing SVP added to roof area. PL-200-A , Proposed Block Plan Existing SVP added and redirected to proposed roof. PL-300-A , Proposed Floor Plans Sink added and hob relocated within the kitchen on the ground floor plan. Existing boiler relocated from the east elevation to the south elevation. South elevation window removed. Office 2 bi-fold door orientation mirrored. PL-301, Proposed Roof Plan Existing SVP added and redirected to proposed roof. PL-500-A, Proposed Elevations Existing boiler relocated from the east elevation to the south elevation. South elevation window removed. Conservatory door added to south elevation. SVP added to all relevant elevations. Office 2 bi-fold door orientation mirrored on the proposed east elevation.