Skip to content

Planning application · EAL/25/00008/SGC

EAL/25/00008/SGCDecidedWorth watching

Scoping opinion for a 2.5 km Newlands Hill power line.

Between The Proposed Newlands Hill Wind Energy Hub and The 400kV Substation Within The Southern Section Of The Existing Fallago Rig Windfarm

East Lothian Council

Preview alerts near this site

Free preview. £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
Renewable Energy, EV & Heat Pumps
Scale
Large 7/10
Tags
  • Associated Infrastructure
  • Eia Scoping
  • Overhead Utility Lines
  • Wind Turbine

Overview

Why it’s worth watching

Major renewable energy infrastructure scoping for a 2.5km 132kV overhead line and cable link serving a wind energy hub.

Proposed
Approximately 2.5 km of 132 kV overhead line
Size
132 kV connection voltage
Stage
Decided: Decided.

The council writes only to properties within 20 metres of an application site. Who is told

Eia required

In plain English

This is a scoping opinion for a proposed section 37 application for the Newlands Hill wind energy hub 132KV Connection Project. It concerns installing approximately 2.5 km of overhead line between the proposed Newlands Hill wind energy hub and the 400kV substation in the southern section of the existing Fallago Rig windfarm. A scoping opinion sets out what an environmental impact assessment should cover.

Written with AI from the application form and the council record.

Keep reading

Track this application

How do I track planning application EAL/25/00008/SGC?

Follow it on City Scope. This page is checked against the East Lothian Council planning register and shows the latest status, decision and documents for EAL/25/00008/SGC. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the East Lothian Council planning portal.

Set up a planning alert