Planning applicationEAL/25/00008/SGC

Between The Proposed Newlands Hill Wind Energy Hub And The 400kV Substation Within The Southern Section Of The Existing Fallago Rig Windfarm

DecidedWorth watchingRenewable Energy & Sustainability
Planning document
1 / 4
Received

25 November 2025

Validated

25 November 2025

Planning Signals

4 detected traits

Specific
Associated InfrastructureEia ScopingOverhead Utility LinesWind Turbine
AI summary

Scoping opinion for a 2.5km 132kV overhead line and cable link for Newlands Hill wind hub, with access track upgrades and tree works.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application EAL/25/00008/SGC

Between The Proposed Newlands Hill Wind Energy Hub And The 400kV Substation Within The Southern Section Of The Existing Fallago Rig Windfarm

DecidedRenewable Energy, EV & Heat PumpsReceived East Lothian Council

Scoping opinion for a 2.5km 132kV overhead line and cable link for Newlands Hill wind hub, with access track upgrades and tree works.

Reference
EAL/25/00008/SGC
Address
Between The Proposed Newlands Hill Wind Energy Hub And The 400kV Substation Within The Southern Section Of The Existing Fallago Rig Windfarm
Status
Decided
Category
Renewable Energy, EV & Heat Pumps
Impact scale
7/10
Authority
East Lothian Council
Received
Validated
Last scraped
Record created
Latitude
55.9549
Longitude
-2.7808

Plain-language summary

Scoping opinion for a 2.5km 132kV overhead line and cable link for Newlands Hill wind hub, with access track upgrades and tree works.

As filed with the council

Scoping opinion for proposed section 37 application for Newlands Hill wind energy hub 132KV Connection Project for installation of approximately 2.5 km of 132 kv OHL (Overhead Line) (ECU00006281)