Scoping opinion for a 2.5km 132kV overhead line and cable link for Newlands Hill wind hub, with access track upgrades and tree works.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application 25/00008/SGC

Between The Proposed Newlands Hill Wind Energy Hub And The 400kV Substation Within The Southern Section Of The Existing Fallago Rig Windfarm

DecidedRenewable Energy, EV & Heat PumpsReceived Local authority

Scoping opinion for a 2.5km 132kV overhead line and cable link for Newlands Hill wind hub, with access track upgrades and tree works.

Reference
25/00008/SGC
Address
Between The Proposed Newlands Hill Wind Energy Hub And The 400kV Substation Within The Southern Section Of The Existing Fallago Rig Windfarm
Status
Decided
Category
Renewable Energy, EV & Heat Pumps
Impact scale
7/10
Authority
Local authority
Received
Validated
Last scraped
Record created

Plain-language summary

Scoping opinion for a 2.5km 132kV overhead line and cable link for Newlands Hill wind hub, with access track upgrades and tree works.

As filed with the council

Scoping opinion for proposed section 37 application for Newlands Hill wind energy hub 132KV Connection Project for installation of approximately 2.5 km of 132 kv OHL (Overhead Line) (ECU00006281)