Planning application · EAL/25/00009/SCR

EAL/25/00009/SCRDecidedWorth watching

A 6km overhead line proposed between Newlands Hill and Fallago Rig.

Newlands Hill Wind Farm

East Lothian Council

Preview alerts near this site

Free preview. £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
Renewable Energy, EV & Heat Pumps
Scale
Large 8/10
Tags
  • Associated Infrastructure
  • Eia Scoping
  • Overhead Utility Lines
  • Rail Infrastructure
  • Railway Infrastructure

Overview

Why it’s worth watching

Major 6km overhead line and associated works linking a wind energy hub to a substation, with clear infrastructure and renewable energy significance.

Today
The existing Fallago Rig Wind Farm includes a 400kV substation in its southern section.
Proposed
A wooden-pole overhead line, approximately 6km long, with associated cabling, accesses and laydown areas.
Size
132 kV line voltage · 6 km approximate line length
Stage
Decided: Decided.

The council writes only to properties within 20 metres of an application site. Who is told

Document 1

In plain English

The proposal is for a 132kV overhead line carried on wooden poles, approximately 6km long. It would connect the proposed Newlands Hill Wind Energy Hub to the 400kV substation in the southern section of the existing Fallago Rig Wind Farm. Associated works include cabling, access routes and laydown areas. The description gives the related reference ECU00006201.

Written with AI from the application form and the council record.

Keep reading

Track this application

How do I track planning application EAL/25/00009/SCR?

Follow it on City Scope. This page is checked against the East Lothian Council planning register and shows the latest status, decision and documents for EAL/25/00009/SCR. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the East Lothian Council planning portal.

Set up a planning alert