Planning application · EAY/25/0001/S37SCR
Screening requested for a new 132 kV overhead line east of New Cumnock.
Greenburn 132KV Connection Project 5.5km To East Of New Cumnock East Ayrshire
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- New-Build & Major Development
- Large 7/10
- Eia Screening
- Overhead Utility Lines
- Wooden Pole
Overview
- Proposed
- A new 132 kilovolt overhead line supported by Trident H wood poles
- Size
- 132 kilovolt (kV) proposed line voltage
- Stage
- Council responded on 11 Dec 2025: EIA not required.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application asks East Ayrshire Council for a screening opinion on a new 132 kilovolt overhead line, supported by Trident H wood poles. A screening opinion is the council’s view on whether a project needs an environmental impact assessment. The council’s recorded decision is that an environmental impact assessment is not required.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
621 of 673 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 52 records from that period are still being added or checked.
Proposals and decisions come from East Ayrshire Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application EAY/25/0001/S37SCR?
Follow it on City Scope. This page is checked against the East Ayrshire Council planning register and shows the latest status, decision and documents for EAY/25/0001/S37SCR. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the East Ayrshire Council planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
A new overhead line supported by Trident H wood poles is proposed.
Questions
Does the project need an environmental impact assessment?
The council’s recorded decision is that an environmental impact assessment is not required.
Tags
- Eia Screening
- Overhead Utility Lines
- Wooden Pole
What each tag is based on
- Eia Screening
- “Request for Screening Opinion”
- Overhead Utility Lines
- “132 kilovolt (kV) overhead line (OHL)”
- Wooden Pole
- “supported by Trident H wood poles”
Where it’s at
The council has responded on 11 December 2025.
- Received19 Nov 2025
- Validated19 Nov 2025The council has everything it needs.
- Comments closed10 Dec 2025Usual deadline. Late comments may still count.
- Target decision19 Jan 20262-month target for local developments.
- Decision11 Dec 2025EIA not required.
The record
- Reference
- EAY/25/0001/S37SCR
- Address
- Greenburn 132KV Connection Project 5.5km To East Of New Cumnock East Ayrshire
- Status
- Decided
- Council decision
- EIA not required
- Decision issued
- Category
- New-Build & Major Development
- Impact scale
- 7/10
- Authority
- East Ayrshire Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.