Planning application · EAY/25/0005/S36SCR
Screening request for 16km power line between wind farm and substation.
Sclenteuch Wind Farm
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- Legal / Administrative
- Large 8/10
- Eia Screening
- Overhead Utility Lines
- Substation Connection Works
- Wind Turbine
Overview
Why it’s worth watching
The screening opinion request concerns a new approximately 16km 132kV overhead line running from the proposed Sclenteuch Wind Farm to Coylton Substation, a significant energy infrastructure project.
- Proposed
- A new 132 kV overhead line, approximately 16km long
- Stage
- Council responded on 4 Sept 2025: EIA not required.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application asks whether an environmental impact assessment (EIA), a detailed study of likely environmental effects, is needed for a new 132 kV overhead line (OHL) between the proposed Sclenteuch Wind Farm and Coylton Substation. The line would be supported by trident “H” poles. The decision was that an EIA is not required.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
621 of 673 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 52 records from that period are still being added or checked.
Proposals and decisions come from East Ayrshire Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application EAY/25/0005/S36SCR?
Follow it on City Scope. This page is checked against the East Ayrshire Council planning register and shows the latest status, decision and documents for EAY/25/0005/S36SCR. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the East Ayrshire Council planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
A new overhead line would run between the proposed Sclenteuch Wind Farm in the south and Coylton Substation in the north.
- 02
The line would be carried on trident “H” poles, typically 11 to 16 metres high.
Questions
What was decided?
The decision was that an environmental impact assessment is not required.
Tags
- Eia Screening
- Overhead Utility Lines
- Substation Connection Works
- Wind Turbine
What each tag is based on
- Eia Screening
- “Screening Opinion Request”
- Overhead Utility Lines
- “132 kV OHL”
- Substation Connection Works
- “existing Coylton Substation”
- Wind Turbine
- “Sclenteuch Wind Farm”
As lodged
The drawings.
Where it’s at
The council has responded on 4 September 2025.
- Received30 Jul 2025
- Validated30 Jul 2025The council has everything it needs.
- Comments closed20 Aug 2025Usual deadline. Late comments may still count.
- Target decision30 Sept 20252-month target for local developments.
- Decision4 Sept 2025EIA not required.
The record
- Reference
- EAY/25/0005/S36SCR
- Address
- Sclenteuch Wind Farm
- Status
- Decided
- Council decision
- EIA not required
- Decision issued
- Category
- Legal / Administrative
- Impact scale
- 8/10
- Authority
- East Ayrshire Council
- Received
- Validated
- Last checked
- Added to City Scope