Planning applicationFIF/22/03982/NMV1

Land For Proposed 20MWp Solar Development Parkend Crossgates Fife

DecidedLegal / Administrative
Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

30 September 2025

Validated

30 September 2025

Planning Signals

4 detected traits

Works
Solar
Specific
Non Material VariationRenewable Energy InfrastructureSubstation
AI summary

Non-material variation for changes to solar park substation arrangements, including customer substation metering structures.

Impact scale

Estimated scale of impact on the surrounding area.

2/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application FIF/22/03982/NMV1

Land For Proposed 20MWp Solar Development Parkend Crossgates Fife

DecidedLegal / AdministrativeReceived Fife Council

Non-material variation for changes to solar park substation arrangements, including customer substation metering structures.

Reference
FIF/22/03982/NMV1
Address
Land For Proposed 20MWp Solar Development Parkend Crossgates Fife
Status
Decided
Category
Legal / Administrative
Impact scale
2/10
Authority
Fife Council
Received
Validated
Last scraped
Record created
Latitude
56.082953
Longitude
-3.374334

Plain-language summary

Non-material variation for changes to solar park substation arrangements, including customer substation metering structures.

As filed with the council

Non-material variation for alterations to substations to 22/03982/FULL