Planning applicationFIF/25/02273/SCR

Middle Balbeggie Farmhouse Balbeggie Avenue Balbeggie Thornton Fife KY1 3NS

WithdrawnWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

11 August 2025

Validated

5 September 2025

Planning Signals

3 detected traits

Specific
Eia ScreeningSection 42 VariationWind Turbine
Application Insights

No form insights available yet.

AI summary

EIA screening request to vary conditions for the existing wind farm, extending operational life and changing the end-of-life trigger timing.

Impact scale

Estimated scale of impact on the surrounding area.

2/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application FIF/25/02273/SCR

Middle Balbeggie Farmhouse Balbeggie Avenue Balbeggie Thornton Fife KY1 3NS

WithdrawnRenewable Energy, EV & Heat PumpsReceived Fife Council

EIA screening request to vary conditions for the existing wind farm, extending operational life and changing the end-of-life trigger timing.

Reference
FIF/25/02273/SCR
Address
Middle Balbeggie Farmhouse Balbeggie Avenue Balbeggie Thornton Fife KY1 3NS
Status
Withdrawn
Category
Renewable Energy, EV & Heat Pumps
Impact scale
2/10
Authority
Fife Council
Received
Validated
Last scraped
Record created
Latitude
56.1518
Longitude
-3.1621

Plain-language summary

EIA screening request to vary conditions for the existing wind farm, extending operational life and changing the end-of-life trigger timing.

As filed with the council

EIA screening opinion request in respect of the development the subject of planning permission 14/02038/FULL, with varied conditions 1 and 4 to extend the operational life of the wind farm from 25 years to 40 years and increase the period before it is deemed no longer required from 6 months to 12 months