Planning applicationFIF/25/02603/FULL

Proposed Development East Of Guardbridge Primary Main Street Guardbridge Fife

RegisteredMechanical Plant, Flues & Ventilation
Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

17 September 2025

Validated

20 November 2025

Planning Signals

2 detected traits

Specific
Associated WorksSubstation
Application Insights

No form insights available yet.

AI summary

Proposed primary electricity sub-station at Bonnybridge Depot with associated site works at Falkirk Road to support grid supply.

Impact scale

Estimated scale of impact on the surrounding area.

4/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application FIF/25/02603/FULL

Proposed Development East Of Guardbridge Primary Main Street Guardbridge Fife

RegisteredMechanical Plant, Flues & VentilationReceived Fife Council

Proposed primary electricity sub-station at Bonnybridge Depot with associated site works at Falkirk Road to support grid supply.

Reference
FIF/25/02603/FULL
Address
Proposed Development East Of Guardbridge Primary Main Street Guardbridge Fife
Status
Registered
Category
Mechanical Plant, Flues & Ventilation
Impact scale
4/10
Authority
Fife Council
Received
Validated
Last scraped
Record created
Latitude
56.3659
Longitude
-2.8924

Plain-language summary

Proposed primary electricity sub-station at Bonnybridge Depot with associated site works at Falkirk Road to support grid supply.

As filed with the council

Formation of primary electricity sub-station and associated works