Skip to content

Planning application · FIF/25/03297/EIA

FIF/25/03297/EIAAwaiting decisionWorth watching

Underground power cables proposed from Westfield to Kinghorn.

HVDC Link From Westfield Substation To South Of A921 Kinghorn Fife

Fife Council

Free with a City Scope account. One email, when the council decides.

Also email me new applications in this council · £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
Telecommunications
Scale
Large 7/10
Tags
  • Associated Infrastructure
  • Cable Route Access
  • Cable Routing
  • Drainage Wastewater Infrastructure
  • Electrical Infrastructure

Overview

Why it’s worth watching

A major energy transmission project crossing Fife with associated compounds and access works has substantial public and infrastructure significance.

Today
The cable routes are largely on agricultural land and settlement margins.
Proposed
Underground direct and alternating current cables, with associated infrastructure and temporary works.
Size
266.90 ha site area
Stage
Past its target date of 19 Jun 2026.

The council writes only to properties within 20 metres of an application site. Who is told

Psad

In plain English

The application seeks full planning permission for underground high-voltage direct and alternating current cables as part of the Eastern Green Link 4 connection between Fife and Norfolk. The route would run from a proposed converter station east of Westfield Substation to a landfall north of Kinghorn, with associated infrastructure including temporary compounds, drainage and accesses. The application also describes temporary works such as access bellmouths, which are widened entrances from roads. It refers to earlier pre-application discussions under references 24/03149/SCO, 23/01019/PREAPP and 24/00157/PREAPP.

Written with AI from the application form and the council record.

Keep reading

Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register

Track this application

How do I track planning application FIF/25/03297/EIA?

Follow it on City Scope. This page is checked against the Fife Council planning register and shows the latest status, decision and documents for FIF/25/03297/EIA. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the Fife Council planning portal.

Set up a planning alert