Planning applicationFIF/26/01047/NEA

Westfield Substation Fife

DecidedLegal / Administrative
Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

27 March 2026

Validated

27 March 2026

Planning Signals

3 detected traits

Specific
Overhead Utility LinesSubstationTemporary Development
AI summary

Notification for a temporary diversion of the 132kV overhead line (approx. 913m) and replacement of a nearby tower to support EGL4 works.

Impact scale

Estimated scale of impact on the surrounding area.

5/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application FIF/26/01047/NEA

Westfield Substation Fife

DecidedLegal / AdministrativeReceived Fife Council

Notification for a temporary diversion of the 132kV overhead line (approx. 913m) and replacement of a nearby tower to support EGL4 works.

Reference
FIF/26/01047/NEA
Address
Westfield Substation Fife
Status
Decided
Category
Legal / Administrative
Impact scale
5/10
Authority
Fife Council
Received
Validated
Last scraped
Record created
Latitude
56.2082078
Longitude
-3.1495175

Plain-language summary

Notification for a temporary diversion of the 132kV overhead line (approx. 913m) and replacement of a nearby tower to support EGL4 works.

As filed with the council

Notification under The Overhead Lines (Exemption) (Scotland) Regulations 2013 for temporary diversion of 132kV Overhead Line and replacement of Tower