Planning applicationFIF/26/01243/PPP

Land To The North Of Camilla Road Gleniston Auchtertool Fife

RegisteredWorth watchingNew-Build & Major Development
Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

29 April 2026

Validated

21 May 2026

Planning Signals

11 detected traits

Works
Boundary Treatment
Specific
Ancillary StructureAssociated InfrastructureCar ParkingClass 6 Storage And DistributionData Centre
Application Insights

No form insights available yet.

AI summary

In-principle plan for a Class 6 data centre campus with data halls, gatehouses, substations, access roads, parking, drainage, fencing and landscaping.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application FIF/26/01243/PPP

Land To The North Of Camilla Road Gleniston Auchtertool Fife

RegisteredNew-Build & Major DevelopmentReceived Fife Council

In-principle plan for a Class 6 data centre campus with data halls, gatehouses, substations, access roads, parking, drainage, fencing and landscaping.

Reference
FIF/26/01243/PPP
Address
Land To The North Of Camilla Road Gleniston Auchtertool Fife
Status
Registered
Category
New-Build & Major Development
Impact scale
8/10
Authority
Fife Council
Received
Validated
Last scraped
Record created
Latitude
56.10281999999999
Longitude
-3.2576839

Plain-language summary

In-principle plan for a Class 6 data centre campus with data halls, gatehouses, substations, access roads, parking, drainage, fencing and landscaping.

As filed with the council

Planning permission in principle for a data centre campus (Class 6) comprising data hall buildings, gatehouses and associated infrastructure including electricity substations, fencing, plant and machinery, access roads, paths, parking, drainage and landscaping