Three new 275kV downleads proposed at Longannet Substation.

Scottish Government Consultation Fife

Fife Council

Preview alerts for this council

Free preview. £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
New-Build & Major Development
Scale
Medium 6/10
Tags
  • Ancillary Structure
  • Associated Infrastructure
  • Overhead Utility Lines
  • Substation

Overview

Today
Existing tower YG001
Proposed
Three new 275kV downleads to a proposed Cable Sealing End compound
Size
3 at 275kV new downleads
Stage
Decided on 21 Aug 2026: Case Closed.

The council writes only to properties within 20 metres of an application site. Who is told

In plain English

The application concerns construction and operation of three new 275kV downleads between existing tower YG001 and a proposed Cable Sealing End compound at Longannet Substation. It is listed as the Alcemi Devilla BESS Overhead Line Grid Connection, reference ECU00006348. Fife Council's record says the case is closed.

Written with AI from the application form and the council record.

Keep reading

Official records · coverage in progress

2,968 of 3,141 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 173 records from that period are still being added or checked.

Proposals and decisions come from Fife Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register

Track this application

How do I track planning application FIF/26/01851/CON?

Follow it on City Scope. This page is checked against the Fife Council planning register and shows the latest status, decision and documents for FIF/26/01851/CON. City Scope can also email you when a new application is lodged in this council area. To comment on the application, use the Fife Council planning portal.

Set up a planning alert