Planning application · HARINGEY/HGY/2025/3384
Details submitted to discharge highways access and construction traffic management requirements for the National Grid north London reinforcement project.
National Grid Overhead Electric Line, Part Adjacent To River Lee Navigation, Brimsdown Substation, Mollison Avenue,, Enfield
- Legal / Administrative
- Minor 1/10
Overview
- Stage
- Council responded: No Objection.
As lodged with the council
Details submitted to discharge Requirement 7 highways access and Requirement 9 Construction Traffic Management Plan (Stage 5d) in relation to the National Grid (north London reinforcement project) order 2014 (Observations to L.B. Enfield - their planning reference 25/04015/DCO)
The headline is a plain-English summary written with AI from the council record.
Keep reading
Track this application
How do I track planning application HARINGEY/HGY/2025/3384?
Follow it on City Scope. This page is checked against the Haringey planning register and shows the latest status, decision and documents for HARINGEY/HGY/2025/3384. To comment on the application, use the Haringey planning portal.
The impact
What it involves.
Where it’s at
The council has responded.
- Validated26 Nov 2025The council has everything it needs.
- Comments closed17 Dec 2025Usual deadline. Late comments may still count.
- Target decision21 Jan 20268-week target for minor and other applications.
- DecisionNo Objection
The record
- Reference
- HARINGEY/HGY/2025/3384
- Address
- National Grid Overhead Electric Line, Part Adjacent To River Lee Navigation, Brimsdown Substation, Mollison Avenue,, Enfield
- Status
- Decision Made
- Council decision
- No Objection
- Category
- Legal / Administrative
- Impact scale
- 1/10
- Authority
- Haringey
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.