Proposed 12 EV charging points, four urban canopies, ancillary amenity block, substation, toilets, CCTV, landscaping and boundary works.
Stanmore, Land Adjacent to Stanmore Station
- Renewable Energy, EV & Heat Pumps
- Medium 6/10
Overview
- Stage
- Past its target date of 6 Aug 2026.
As lodged with the council
Installation of 12 electric vehicle charging points; Four urban canopies; Unmanned ancillary amenity block; Substation and LV Pillar; Toilet facilities; CCTV; Landscaping, Boundary treatments and associated works
The headline is a plain-English summary written with AI from the council record.
Keep reading
Track this application
How do I track planning application HARROW/PL/1418/26?
Follow it on City Scope. This page is checked against the Harrow planning register and shows the latest status, decision and documents for HARROW/PL/1418/26. To comment on the application, use the Harrow planning portal.
The impact
What it involves.
Drawings
Where the site is.
On the map
Open the planning map →© MapTiler © OpenStreetMap contributors
Where it’s at
Comments have closed. The target date for a decision has passed.
- Validated11 Jun 2026The council has everything it needs.
- Comments closed2 Jul 2026Usual deadline. Late comments may still count.
- Target decision (next)6 Aug 20268-week target for minor and other applications.
- DecisionNot yet
Planning terms
- Ancillary
- Part of the main use rather than a separate business. An ancillary hotel bar serves the hotel.
The record
- Reference
- HARROW/PL/1418/26
- Address
- Stanmore, Land Adjacent to Stanmore Station
- Status
- Application Under Consideration
- Category
- Renewable Energy, EV & Heat Pumps
- Impact scale
- 6/10
- Authority
- Harrow
- Validated
- Last checked
- Added to City Scope