Erection and operation of a 10.5km 132kV overhead electricity line, approximately 3 km to the north of Lairg between Chleansaid Wind Farm and Dalchork Substation. This case will be determined by the Energy Consents Unit Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationDetails.aspx?cr=ECU00004894 using reference number ECU00004894
Keep reading
Official records · coverage in progress
2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.
Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application HLD/25/00106/S37?
Follow it on City Scope. This page is checked against the Highland Council planning register and shows the latest status, decision and documents for HLD/25/00106/S37. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the Highland Council planning portal.
Set up a planning alertAs lodged
The drawings.
All documents (4)
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
The council has decided on 16 February 2026.
- Received9 Jan 2025
- Validated9 Jan 2025The council has everything it needs.
- Comments closed30 Jan 2025Usual deadline. Late comments may still count.
- Target decision9 Mar 20252-month target for local developments.
- Decision16 Feb 2026Approved by Scottish Ministers.
The record
- Reference
- HLD/25/00106/S37
- Address
- Chleansaid Wind Farm Dalnessie Rogart
- Status
- Decided
- Council decision
- Approved by Scottish Ministers
- Decision issued
- Authority
- The Highland Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.