Planning applicationHLD/25/02861/S36

Land 1500M SE Of Borlum House Reay

Awaiting decisionWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.

Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

31 July 2025

Validated

31 July 2025

Planning Signals

5 detected traits

Works
House Extension
Specific
Associated InfrastructureSection 36 ConsentSubstationWind Turbine
Application Insights

No form insights available yet.

AI summary

Plans for a BESS (50MW+) at Limekiln Wind Farm, adding substation extensions, access and ancillary infrastructure for grid storage.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/25/02861/S36

Land 1500M SE Of Borlum House Reay

Awaiting decisionRenewable Energy, EV & Heat PumpsReceived The Highland Council

Plans for a BESS (50MW+) at Limekiln Wind Farm, adding substation extensions, access and ancillary infrastructure for grid storage.

Reference
HLD/25/02861/S36
Address
Land 1500M SE Of Borlum House Reay
Status
Awaiting decision
Category
Renewable Energy, EV & Heat Pumps
Impact scale
6/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
58.5469
Longitude
-3.7534

Plain-language summary

Plans for a BESS (50MW+) at Limekiln Wind Farm, adding substation extensions, access and ancillary infrastructure for grid storage.

As filed with the council

Limekiln Battery Energy Storage System (BESS) - Construction and operation of a proposed Battery Energy Storage System (BESS) (over 50 MW) and an extension to the existing Limekiln Wind Farm Substation, associated infrastructure, access and ancillary works. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00006154