Planning applicationHLD/25/03055/FUL

Land 4.4KM SW Of North Laggan Farmhouse North Laggan

Under ConsiderationWorth watchingNew-Build & Major Development
Official records · coverage in progress

2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.

Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

16 August 2025

Validated

3 October 2025

Planning Signals

11 detected traits

Specific
Ancillary StructureAssociated InfrastructureCable RoutingHydroelectric Power StationRail InfrastructureRailway Infrastructure
Application Insights

No form insights available yet.

AI summary

Coire Glas pumped-storage scheme: tunnel and portal works, access tracks and cable trenching proposed to link generating station to the national grid.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/25/03055/FUL

Land 4.4KM SW Of North Laggan Farmhouse North Laggan

Under ConsiderationNew-Build & Major DevelopmentReceived The Highland Council

Coire Glas pumped-storage scheme: tunnel and portal works, access tracks and cable trenching proposed to link generating station to the national grid.

Reference
HLD/25/03055/FUL
Address
Land 4.4KM SW Of North Laggan Farmhouse North Laggan
Status
Under Consideration
Category
New-Build & Major Development
Impact scale
8/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
57.0398
Longitude
-4.8723

Plain-language summary

Coire Glas pumped-storage scheme: tunnel and portal works, access tracks and cable trenching proposed to link generating station to the national grid.

As filed with the council

Coire Glas Hydro Pumped Storage Scheme - Construction of tunnel, tunnel portal & portal apron (tunnel inclusive of passing places, turning niches & refuge areas) to accommodate installation of 400kV export/import electricity cables to connect Coire Glas generating station to the national grid, including access tracks with surface cable trenching, temporary construction compounds to include but not limited to welfare, parking, plant, materials storage & materials processing, ancillary buildings & spoil storage areas.