Planning application · HLD/25/04439/SCOP
15 km overhead line proposed from Coire Glas to Auchterawe.
Land 1960M NE Of Faichem Hydro Electric Scheme Faichem Invergarry
Free with a City Scope account. One email, when the council decides.
Also email me new applications nearby · £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- New-Build & Major Development
- Large 8/10
- Eia Scoping
- Hydroelectric Power Station
- Overhead Line Double Circuit Schedule 8
- Steel Lattice Tower Replacement Removal
- Substation
Overview
Why it’s worth watching
This is major electricity transmission infrastructure with significant landscape and visual implications across a recognised Highland area.
- Proposed
- A new overhead line and a substation at Loch Lundie.
- Size
- 400 kV line voltage · 400 / 132 kV proposed substation voltage
- Stage
- Past its target date of 19 Jan 2026.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application describes a new double-circuit 400 kV overhead line, supported by steel lattice towers, to connect the consented Coire Glas Hydro Pumped Storage project to the electricity network. The route would reach the existing Fort Augustus substation at Auchterawe via a proposed new 400 / 132 kV substation at Loch Lundie.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.
Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application HLD/25/04439/SCOP?
Follow it on City Scope. This page is checked against the Highland Council planning register and shows the latest status, decision and documents for HLD/25/04439/SCOP. City Scope can email you when this application is decided, free with a City Scope account. To comment on the application, use the Highland Council planning portal.
On the street
What neighbours would notice.
- 01
The overhead line would be supported on steel lattice towers.
- 02
A new substation is proposed at Loch Lundie.
Tags
- Eia Scoping
- Hydroelectric Power Station
- Overhead Line Double Circuit Schedule 8
- Steel Lattice Tower Replacement Removal
- Substation
What each tag is based on
- Eia Scoping
- “25/04439/SCOP”
- Hydroelectric Power Station
- “Connect the consented Coire Glas Hydro Pumped Storage project”
- Overhead Line Double Circuit Schedule 8
- “new double circuit 400 kV overhead line”
- Steel Lattice Tower Replacement Removal
- “supported on steel lattice towers”
- Substation
- “proposed new 400 / 132 kV substation at Loch Lundie”
As lodged
The drawings.
All documents (4)
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
Comments have closed. The target date for a decision has passed.
- Received19 Nov 2025
- Validated19 Nov 2025The council has everything it needs.
- Comments closed10 Dec 2025Usual deadline. Late comments may still count.
- Target decision (next)19 Jan 20262-month target for local developments.
- DecisionNot yet
The record
- Reference
- HLD/25/04439/SCOP
- Address
- Land 1960M NE Of Faichem Hydro Electric Scheme Faichem Invergarry
- Status
- Under Consideration
- Category
- New-Build & Major Development
- Impact scale
- 8/10
- Authority
- The Highland Council
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.