Planning applicationHLD/26/00340/FUL

Land 290M SW Of Kinloch House Lochcarron

DecidedWorth watchingParking, Access & Highways
Official records · coverage in progress

2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.

Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

27 January 2026

Validated

27 February 2026

Planning Signals

7 detected traits

Specific
Active Travel RouteAssociated InfrastructureBorrow PitBorrow Pit Restoration BackfillForestry Access TrackPedestrian Infrastructure
Application Insights

No form insights available yet.

AI summary

Temporary track widening for construction haul road, then all-abilities path and footpath upgrades; borrow-pit works to supply materials and restore the pit.

Impact scale

Estimated scale of impact on the surrounding area.

5/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/26/00340/FUL

Land 290M SW Of Kinloch House Lochcarron

DecidedParking, Access & HighwaysReceived The Highland Council

Temporary track widening for construction haul road, then all-abilities path and footpath upgrades; borrow-pit works to supply materials and restore the pit.

Reference
HLD/26/00340/FUL
Address
Land 290M SW Of Kinloch House Lochcarron
Status
Decided
Category
Parking, Access & Highways
Impact scale
5/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
57.4102
Longitude
-5.4811

Plain-language summary

Temporary track widening for construction haul road, then all-abilities path and footpath upgrades; borrow-pit works to supply materials and restore the pit.

As filed with the council

Temporary upgrading/widening of existing track for construction haul road, followed by formation of all abilities path; improvements to existing footpaths; and works to extract materials from former borrow pit for path formation and restoration of borrow pit