CityScope · Planning Updates
Application HLD/26/00733/S37
Land 550M NW Of Brabster Farm Cottage Canisbay
Plans for ~8.6km 132kV overhead powerline on double wood pole structures between Slickly substation and Gills Bay switching station.
The record
- Reference
- HLD/26/00733/S37
- Address
- Land 550M NW Of Brabster Farm Cottage Canisbay
- Status
- Decided
- Category
- Renewable Energy, EV & Heat Pumps
- Impact scale
- 7/10
- Authority
- The Highland Council
Timeline
- Received
- Validated
- Last scraped
- Record created
Additional application data
- Latitude
- 58.607
- Longitude
- -3.1754
What is proposed
Plain-language summary
Plans for ~8.6km 132kV overhead powerline on double wood pole structures between Slickly substation and Gills Bay switching station.
As filed with the council
Slickly Windfarm Connection - Installation of approximately 8.6 km of 132 kV single circuit overhead line supported on trident double wood pole structures between Slickly Substation and Gills Bay Switching Station. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00005075