Planning document
1 / 4
Received

20 March 2026

Validated

20 March 2026

Planning Signals

9 detected traits

Specific
Access RoadsAssociated InfrastructureBorrow PitRail InfrastructureRailway InfrastructureRailway Station
Application Insights

No form insights available yet.

AI summary

Erecting a large wind farm with battery storage, access tracks and substationup to 40 years proposed operation with very tall turbines.

Impact scale

Estimated scale of impact on the surrounding area.

9/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/26/01226/S36

Land 3Km SW Of Wester Lealty At Cnoc Ceislain Novar Evanton

Under ConsiderationRenewable Energy, EV & Heat PumpsReceived The Highland Council

Erecting a large wind farm with battery storage, access tracks and substationup to 40 years proposed operation with very tall turbines.

Reference
HLD/26/01226/S36
Address
Land 3Km SW Of Wester Lealty At Cnoc Ceislain Novar Evanton
Status
Under Consideration
Category
Renewable Energy, EV & Heat Pumps
Impact scale
9/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
57.6999
Longitude
-4.38

Plain-language summary

Erecting a large wind farm with battery storage, access tracks and substationup to 40 years proposed operation with very tall turbines.

As filed with the council

Ceislein Wind Farm - Erection and operation of a wind farm for a period of 40 years, comprising up to 11 wind turbines with a maximum blade tip height of 250m, (8 turbines at 250m Nos. T3 through to T10, and 3 turbines at 200m, Nos T1, T2 and T11), Battery Energy Storage System, access tracks, borrow pits, substation, control building, and ancillary infrastructure. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00005174