Planning applicationHLD/26/02214/SCRE

Land 570M NW Of Shalmstry Thurso

Awaiting decisionWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.

Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

18 May 2026

Validated

18 May 2026

Planning Signals

8 detected traits

Works
Landscaping
Specific
Drainage Wastewater InfrastructureEia ScreeningExternal LightingSubstationSwitchgear Switching Equipment Enclosure
Application Insights

No form insights available yet.

AI summary

Grid stability facility with synchronous condenser/flywheel, control building and switchgear, SuDS drainage and lighting, plus underground high-voltage cable to Thurso South substation.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/26/02214/SCRE

Land 570M NW Of Shalmstry Thurso

Awaiting decisionRenewable Energy, EV & Heat PumpsReceived The Highland Council

Grid stability facility with synchronous condenser/flywheel, control building and switchgear, SuDS drainage and lighting, plus underground high-voltage cable to Thurso South substation.

Reference
HLD/26/02214/SCRE
Address
Land 570M NW Of Shalmstry Thurso
Status
Awaiting decision
Category
Renewable Energy, EV & Heat Pumps
Impact scale
6/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
58.5626
Longitude
-3.5065

Plain-language summary

Grid stability facility with synchronous condenser/flywheel, control building and switchgear, SuDS drainage and lighting, plus underground high-voltage cable to Thurso South substation.

As filed with the council

Erection of a grid stability facility (synchronous condenser and flywheel) and associated infrastructure, including control building, transformers, switchgear, access, parking, boundary enclosures, drainage (including SuDS), lighting and landscaping, together with an associated high voltage underground cable connection to Thurso South Substation.