Planning applicationHLD/26/04116/PAN

Land 1.3KM SE Of Strathmashie Cottage Strathmashie Laggan

Under ConsiderationWorth watchingNew-Build & Major Development
Official records · coverage in progress

2,581 of 2,786 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 205 records from that period are still being added or checked.

Proposals and decisions come from The Highland Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
Received

15 September 2026

Validated

15 September 2026

Planning Signals

5 detected traits

Specific
Kilovolt Voltage Category 33kv Overhead LineProposal Of Application NoticeSteel Lattice Tower Replacement RemovalSubstation Connection WorksUtility Line Route Corridor
Application Insights

No form insights available yet.

AI summary

Coire Mashie Project: proposed two 400 kV steel lattice towers and new overhead line sections to tie the Beauly-Denny line into a proposed substation.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application HLD/26/04116/PAN

Land 1.3KM SE Of Strathmashie Cottage Strathmashie Laggan

Under ConsiderationNew-Build & Major DevelopmentReceived The Highland Council

Coire Mashie Project: proposed two 400 kV steel lattice towers and new overhead line sections to tie the Beauly-Denny line into a proposed substation.

Reference
HLD/26/04116/PAN
Address
Land 1.3KM SE Of Strathmashie Cottage Strathmashie Laggan
Status
Under Consideration
Category
New-Build & Major Development
Impact scale
6/10
Authority
The Highland Council
Received
Validated
Last scraped
Record created
Latitude
56.994919
Longitude
-4.329715

Plain-language summary

Coire Mashie Project: proposed two 400 kV steel lattice towers and new overhead line sections to tie the Beauly-Denny line into a proposed substation.

As filed with the council

Coire Mashie Project - Beauly-Denny Overhead Line Diversion works - Install and operate two new 400 kV steel lattice towers, together with two sections of approximately 0.4km of new overhead line (including a temporary diversion requiring 1.16km requiring new temporary towers) to facilitate the tie-in of the existing Beauly-Denny overhead line into the proposed Coire Mashie 400 kV substation.