Planning applicationMID/26/00450/PAC

Electricity Substation 500M North East of Langside Dalkeith

DecidedWorth watchingNew-Build & Major Development
Planning document
1 / 4
Received

17 August 2026

Validated

17 August 2026

Planning Signals

10 detected traits

Works
House Extension
Specific
Ancillary StructureAssociated InfrastructureAssociated WorksBoundary Fence InstallationElectrical Infrastructure
Application Insights

No form insights available yet.

AI summary

Proposed Smeaton Substation extension with 400kV switching equipment, grid supply infrastructure, construction compound, landscaping and security fencing.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application MID/26/00450/PAC

Electricity Substation 500M North East of Langside Dalkeith

DecidedNew-Build & Major DevelopmentReceived Local authority

Proposed Smeaton Substation extension with 400kV switching equipment, grid supply infrastructure, construction compound, landscaping and security fencing.

Reference
MID/26/00450/PAC
Address
Electricity Substation 500M North East of Langside Dalkeith
Status
Decided
Category
New-Build & Major Development
Impact scale
8/10
Authority
Local authority
Received
Validated
Last scraped
Record created
Latitude
55.89311799999999
Longitude
-3.066606

Plain-language summary

Proposed Smeaton Substation extension with 400kV switching equipment, grid supply infrastructure, construction compound, landscaping and security fencing.

As filed with the council

Proposal of application notice for extension to existing electricity substation including installation of a new 400kv switching bay, new grid supply point electricity equipment, formation of temporary construction compound and landscaping, erection of security fence and gates, and associated works