Planning applicationMOR/25/01364/S37

Beauly To Peterhead

UnknownWorth watchingNew-Build & Major Development
Official records · coverage in progress

696 of 697 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 1 records from that period are still being added or checked.

Proposals and decisions come from Moray Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

16 October 2025

Validated

17 October 2025

Council decision
Objections
Decision issued

Planning Signals

6 detected traits

Specific
Ancillary StructureOverhead Utility LinesSection 37 ConsentSteel Lattice Tower Replacement RemovalSubstationTower Foundation Upgrades And Strengthening
AI summary

Proposed 400kV double-circuit overhead line across NE Scotland, linking new substations near New Deer/Netherton and Peterhead with realignments and diversions.

Impact scale

Estimated scale of impact on the surrounding area.

9/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application MOR/25/01364/S37

Beauly To Peterhead

UnknownNew-Build & Major DevelopmentReceived Moray Council

Proposed 400kV double-circuit overhead line across NE Scotland, linking new substations near New Deer/Netherton and Peterhead with realignments and diversions.

Reference
MOR/25/01364/S37
Address
Beauly To Peterhead
Status
Unknown
Council decision
Objections
Decision issued
Category
New-Build & Major Development
Impact scale
9/10
Authority
Moray Council
Received
Validated
Last scraped
Record created

Plain-language summary

Proposed 400kV double-circuit overhead line across NE Scotland, linking new substations near New Deer/Netherton and Peterhead with realignments and diversions.

As filed with the council

Install operate and keep installed approximately 186 km of new 400 kilovolt (kV) double circuit steel structure overhead transmission line (OHL) including downleads to connect into new substation sites at Fanellan (NH 48321 42717) in the area of Beauly Greens (NJ 81960 47587) in the area of New Deer and Netherton (NK 05761 45576) in the area of Peterhead The Proposed Development also includes crossing work, temporary diversions and permanent realignment works to existing 132 kV and 275 kV OHLs of approximately 14.7 km in total and ancillary development and associated works In total the Proposed Development would comprise approximately 200.7 km of new OHL infrastructure between