Planning applicationNAY/26/00308/EIA

Clydeport Hunterston Terminal Fairlie Largs North Ayrshire KA29 0AZ

Scoping/Screening AgreedWorth watchingRenewable Energy & Sustainability
Official records · coverage in progress

473 of 482 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 9 records from that period are still being added or checked.

Proposals and decisions come from North Ayrshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

29 April 2026

Validated

30 April 2026

Planning Signals

2 detected traits

Specific
Charging InfrastructureEia Screening
AI summary

EIA screening request for an EV charging hub at Hunterston Park, with charging bays, possible new plant/building and grid connections across the site.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application NAY/26/00308/EIA

Clydeport Hunterston Terminal Fairlie Largs North Ayrshire KA29 0AZ

Scoping/Screening AgreedRenewable Energy, EV & Heat PumpsReceived North Ayrshire Council

EIA screening request for an EV charging hub at Hunterston Park, with charging bays, possible new plant/building and grid connections across the site.

Reference
NAY/26/00308/EIA
Address
Clydeport Hunterston Terminal Fairlie Largs North Ayrshire KA29 0AZ
Status
Scoping/Screening Agreed
Category
Renewable Energy, EV & Heat Pumps
Impact scale
6/10
Authority
North Ayrshire Council
Received
Validated
Last scraped
Record created
Latitude
55.7444
Longitude
-4.8634

Plain-language summary

EIA screening request for an EV charging hub at Hunterston Park, with charging bays, possible new plant/building and grid connections across the site.

As filed with the council

EIA Screening request for a proposed electric vehicle (EV) charging hub and its associated infrastructure