132KV Overhead Line Stornoway Wind Farm Connection Lochs Road Lochs Isle Of Lewis
Screening opinion for a 1.6km overhead power line on 1116m trident wood poles linking the Lewis hub to the Stornoway wind farm substation.
The record
- Reference
- NES/25/00259/OHLSCR
- Address
- 132KV Overhead Line Stornoway Wind Farm Connection Lochs Road Lochs Isle Of Lewis
- Status
- Decided
- Category
- Renewable Energy, EV & Heat Pumps
- Impact scale
- 6/10
- Authority
- Comhairle nan Eilean Siar
Timeline
- Received
- Validated
- Last scraped
- Record created
What is proposed
Plain-language summary
Screening opinion for a 1.6km overhead power line on 1116m trident wood poles linking the Lewis hub to the Stornoway wind farm substation.
As filed with the council
SG ECU Consultation on a Screening Opinion for new 132 kilovolt (kV) 1.6km overhead line (OHL) supported by trident wood poles of 11 -16m height, between the proposed Lewis Electricity Transmission Hub (Comhairle nan Eilean Siar reference: 25/00061/PPPM) and the substation at the proposed Stornoway Wind Farm (ECU00001850). The Proposed Development would consist of 1.6 km of OHL