Planning application · NES/26/00050/OHL
New 33Kva overhead line spur proposed at Drimore.
Electric Sub Station Drimore Grogarry Isle Of South Uist
Free preview. £1 a month for one alert. Cancel any time.
Preview alerts near your postcode
- New-Build & Major Development
- Medium 5/10
- Kilovolt Voltage Category 33kv Overhead Line
- Overhead Utility Lines
- Spur Overhead Line Connection
- Substation
- Three Span Spur Overhead Line
Overview
- Proposed
- A new 33Kva overhead line spur with four spans.
- Size
- 33 Kva line capacity · 4 spans
- Stage
- Council responded on 6 Mar 2026: No Objection.
The council writes only to properties within 20 metres of an application site. Who is told
In plain English
The application proposes a new overhead line spur with four spans to accommodate a new substation building. The record gives a decision of “No Objection”.
Written with AI from the application form and the council record.
Keep reading
Official records · coverage in progress
454 of 455 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 1 records from that period are still being added or checked.
Proposals and decisions come from Comhairle nan Eilean Siar. Additional summaries and analysis are being added where verified.
Check the council’s planning registerTrack this application
How do I track planning application NES/26/00050/OHL?
Follow it on City Scope. This page is checked against the Comhairle nan Eilean Siar planning register and shows the latest status, decision and documents for NES/26/00050/OHL. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the Comhairle nan Eilean Siar planning portal.
Set up a planning alertOn the street
What neighbours would notice.
- 01
A new overhead line spur with four spans is proposed.
Questions
What decision is recorded?
The record says “No Objection”.
Tags
- Kilovolt Voltage Category 33kv Overhead Line
- Overhead Utility Lines
- Spur Overhead Line Connection
- Substation
- Three Span Spur Overhead Line
What each tag is based on
- Kilovolt Voltage Category 33kv Overhead Line
- “33Kva overhead line”
- Overhead Utility Lines
- “New 33Kva overhead line Spur”
- Spur Overhead Line Connection
- “overhead line Spur (4 Spans)”
- Substation
- “to accomodate new Substation building”
- Three Span Spur Overhead Line
- “Spur (4 Spans)”
As lodged
The drawings.
All documents (4)
On the map
Open the planning map →© MapTiler / OpenFreeMap © OpenStreetMap contributors
Where it’s at
The council has responded on 6 March 2026.
- Received9 Feb 2026
- Validated9 Feb 2026The council has everything it needs.
- Comments closed2 Mar 2026Usual deadline. Late comments may still count.
- Target decision9 Apr 20262-month target for local developments.
- Decision6 Mar 2026No Objection.
The record
- Reference
- NES/26/00050/OHL
- Address
- Electric Sub Station Drimore Grogarry Isle Of South Uist
- Status
- Decided
- Council decision
- No Objection
- Decision issued
- Category
- New-Build & Major Development
- Impact scale
- 5/10
- Authority
- Comhairle nan Eilean Siar
- Received
- Validated
- Last checked
- Added to City Scope
Discussion
Talk about this application.
Share what you know about the site with other City Scope readers.