Planning applicationNLK/25/01282/PRN

Adjacent To Esso Petrol Station New Edinburgh Road Uddingston North Lanarkshire

Decided - Permitted DevelopmentTelecommunications
Official records · coverage in progress

849 of 945 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 96 records from that period are still being added or checked.

Proposals and decisions come from North Lanarkshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 2
Received

1 December 2025

Validated

1 December 2025

Planning Signals

3 detected traits

Specific
Antenna Count 9Pole Swap With Height IncreaseTelecomms Cabinet
AI summary

Would replace the 14.5m telecom pole with a 20m monopole, add 9 antennas, and update/remove associated cabinets at the base station.

Impact scale

Estimated scale of impact on the surrounding area.

5/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application NLK/25/01282/PRN

Adjacent To Esso Petrol Station New Edinburgh Road Uddingston North Lanarkshire

Decided - Permitted DevelopmentTelecommunicationsReceived North Lanarkshire Council

Would replace the 14.5m telecom pole with a 20m monopole, add 9 antennas, and update/remove associated cabinets at the base station.

Reference
NLK/25/01282/PRN
Address
Adjacent To Esso Petrol Station New Edinburgh Road Uddingston North Lanarkshire
Status
Decided - Permitted Development
Category
Telecommunications
Impact scale
5/10
Authority
North Lanarkshire Council
Received
Validated
Last scraped
Record created
Latitude
55.8204
Longitude
-4.0411

Plain-language summary

Would replace the 14.5m telecom pole with a 20m monopole, add 9 antennas, and update/remove associated cabinets at the base station.

As filed with the council

The proposed upgrade of an existing telecommunications base station comprising removal of 14.5m pole, to be replaced by proposed 20m monopole and the addition of 9 no. new antennas, together with the removal of 1 no. existing cabinet, the internal upgrades to 1 no. meter cabinet and 1 no. equipment cabinet and ancillary development thereto.