Planning applicationORK/25/315/PP

Houton Ferry Terminal And Toilets (Land Near) Houton Road, Orphir, Orkney

DecidedWorth watchingNew-Build & Major Development
Official records · coverage in progress

312 of 345 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 33 records from that period are still being added or checked.

Proposals and decisions come from Orkney Islands Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

18 September 2025

Validated

16 December 2025

Planning Signals

8 detected traits

Works
Landscaping
Specific
Drainage Wastewater InfrastructureGeneratorParking AccessPedestrian InfrastructureTemporary Development
AI summary

Temporary workforce setup: new access road/footpaths, ground profiling, services & drainage, welfare and two accommodation units plus generators, for 12 months.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application ORK/25/315/PP

Houton Ferry Terminal And Toilets (Land Near) Houton Road, Orphir, Orkney

DecidedNew-Build & Major DevelopmentReceived Orkney Islands Council

Temporary workforce setup: new access road/footpaths, ground profiling, services & drainage, welfare and two accommodation units plus generators, for 12 months.

Reference
ORK/25/315/PP
Address
Houton Ferry Terminal And Toilets (Land Near) Houton Road, Orphir, Orkney
Status
Decided
Category
New-Build & Major Development
Impact scale
6/10
Authority
Orkney Islands Council
Received
Validated
Last scraped
Record created
Latitude
58.9184
Longitude
-3.1837

Plain-language summary

Temporary workforce setup: new access road/footpaths, ground profiling, services & drainage, welfare and two accommodation units plus generators, for 12 months.

As filed with the council

Create an access, construct a road and footpaths, profile land to construct platforms and hardstandings, install services and drainage infrastructure, and associated landscaping, and erect two temporary accommodation units and a welfare unit and two generators (12 months)