REN/26/0639/PPAwaiting decisionWorth watching

Changes to approved electricity storage facility near Bishopton.

Site 300 Metres South West Of Shilton Cottage Old Greenock Road Bishopton

Renfrewshire Council

Free with a City Scope account. One email, when the council decides.

Also email me new applications nearby · £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
New-Build & Major Development
Scale
Small 4/10
Tags
  • Ancillary Structure
  • Battery Storage
  • Boundary Treatment
  • Retrospective
  • Substation

Overview

Why it’s worth watching

This is a retrospective amendment to a consented energy storage facility with multiple material layout and infrastructure changes, making it a meaningful piece of local infrastructure.

Today
An operational containerised electricity storage facility with security columns, boundary fence, access and landscaping.
Proposed
Retain the as-built changes, including palisade fencing and gates, a harmonic filter, repositioned equipment, a reduced compound and switchgear building, revised parking and adjusted landscaping.
Size
0.49 ha site area · 4 parking spaces currently · 2 parking spaces proposed
Stage
Past its target date of 14 Oct 2026.

The council writes only to properties within 20 metres of an application site. Who is told

Harmonic filter plan and elevation

In plain English

This application seeks retrospective permission for changes to the containerised electricity storage facility approved under 23/0719/PP. The changes include fencing and gates, a harmonic filter, repositioned equipment, a smaller compound and switchgear building, revised parking and adjusted landscaping. The work was completed on 09/07/2026.

Written with AI from the application form and the council record.

Keep reading

Official records · coverage in progress

689 of 712 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026. 23 records from that period are still being added or checked.

Proposals and decisions come from Renfrewshire Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register

Track this application

How do I track planning application REN/26/0639/PP?

Follow it on City Scope. This page is checked against the Renfrewshire Council planning register and shows the latest status, decision and documents for REN/26/0639/PP. City Scope can email you when this application is decided, free with a City Scope account. To comment on the application, use the Renfrewshire Council planning portal.