Planning applicationSBO/25/01141/FUL

Lamb Hill And Dunside Hill Land At Wind Farm Northwest Of Longformacus Scottish Borders

DecidedTelecommunications
Official records · analysis in progress

1,291 of 1,291 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Scottish Borders Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 3
Received

25 August 2025

Validated

1 September 2025

Planning Signals

3 detected traits

Works
Solar
Specific
Met MastTemporary Development
Application Insights

No form insights available yet.

AI summary

Plans for two temporary 120m meteorological masts with a ground-mounted PV array and associated guy wires, supporting weather monitoring.

Impact scale

Estimated scale of impact on the surrounding area.

7/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application SBO/25/01141/FUL

Lamb Hill And Dunside Hill Land At Wind Farm Northwest Of Longformacus Scottish Borders

DecidedTelecommunicationsReceived Scottish Borders Council

Plans for two temporary 120m meteorological masts with a ground-mounted PV array and associated guy wires, supporting weather monitoring.

Reference
SBO/25/01141/FUL
Address
Lamb Hill And Dunside Hill Land At Wind Farm Northwest Of Longformacus Scottish Borders
Status
Decided
Category
Telecommunications
Impact scale
7/10
Authority
Scottish Borders Council
Received
Validated
Last scraped
Record created
Latitude
55.8318
Longitude
-2.6165

Plain-language summary

Plans for two temporary 120m meteorological masts with a ground-mounted PV array and associated guy wires, supporting weather monitoring.

As filed with the council

Erection of two temporary 120m meteorological masts with ground base PV array