Planning applicationSBO/25/01855/NECON

Newlands Hill Wind Energy Hub South East Of Gifford East Lothian

UnknownWorth watchingRenewable Energy & Sustainability
Official records · analysis in progress

1,291 of 1,291 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Scottish Borders Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
Received

27 June 2025

Validated

27 June 2025

Planning Signals

3 detected traits

Specific
Overhead Utility LinesSection 37 ConsentWind Turbine
AI summary

Plans for installing an overhead 132kV power line of around 2.5km from Newlands Hill Wind Energy Hub to the 400kV substation at Fallago Rig.

Impact scale

Estimated scale of impact on the surrounding area.

8/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application SBO/25/01855/NECON

Newlands Hill Wind Energy Hub South East Of Gifford East Lothian

UnknownRenewable Energy, EV & Heat PumpsReceived Scottish Borders Council

Plans for installing an overhead 132kV power line of around 2.5km from Newlands Hill Wind Energy Hub to the 400kV substation at Fallago Rig.

Reference
SBO/25/01855/NECON
Address
Newlands Hill Wind Energy Hub South East Of Gifford East Lothian
Status
Unknown
Category
Renewable Energy, EV & Heat Pumps
Impact scale
8/10
Authority
Scottish Borders Council
Received
Validated
Last scraped
Record created

Plain-language summary

Plans for installing an overhead 132kV power line of around 2.5km from Newlands Hill Wind Energy Hub to the 400kV substation at Fallago Rig.

As filed with the council

The Proposed Development is for the installation of approximately 2.5 km of 132 kV OHL (Overhead Line), between the proposed Newlands Hill Wind Energy Hub and the 400kV substation within the southern section of the existing Fallago Rig Windfarm