Planning applicationSBO/26/00314/SCR

Millmoor Rig Wind Farm Land South West Of Southdean Lodge Southdean Hawick Scottish Borders

DecidedWorth watchingTelecommunications
Official records · analysis in progress

1,291 of 1,291 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Scottish Borders Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register
Planning document
1 / 4
Received

4 March 2026

Validated

4 March 2026

Planning Signals

4 detected traits

Specific
Eia ScreeningOverhead Utility LinesSubstationWind Turbine
AI summary

Proposed 132kV wood-pole overhead power line, around 25km long, linking Millmoor Rig wind farm substation to Hawick substation.

Impact scale

Estimated scale of impact on the surrounding area.

6/10
DISCUSSION

No comments yet

Be the first to share your local perspective on this application.

CityScope · Planning Updates

Application SBO/26/00314/SCR

Millmoor Rig Wind Farm Land South West Of Southdean Lodge Southdean Hawick Scottish Borders

DecidedTelecommunicationsReceived Scottish Borders Council

Proposed 132kV wood-pole overhead power line, around 25km long, linking Millmoor Rig wind farm substation to Hawick substation.

Reference
SBO/26/00314/SCR
Address
Millmoor Rig Wind Farm Land South West Of Southdean Lodge Southdean Hawick Scottish Borders
Status
Decided
Category
Telecommunications
Impact scale
6/10
Authority
Scottish Borders Council
Received
Validated
Last scraped
Record created
Latitude
55.389
Longitude
-2.8231

Plain-language summary

Proposed 132kV wood-pole overhead power line, around 25km long, linking Millmoor Rig wind farm substation to Hawick substation.

As filed with the council

Installation of 132kV wood pole overheard line, approximately 25km long between Millmoor Rig wind farm substation and Hawick substation