Millmoor Rig Wind Farm Land South West Of Southdean Lodge Southdean Hawick Scottish Borders
Proposed 132kV wood-pole overhead power line, around 25km long, linking Millmoor Rig wind farm substation to Hawick substation.
The record
- Reference
- SBO/26/00314/SCR
- Address
- Millmoor Rig Wind Farm Land South West Of Southdean Lodge Southdean Hawick Scottish Borders
- Status
- Decided
- Category
- Telecommunications
- Impact scale
- 6/10
- Authority
- Scottish Borders Council
Timeline
- Received
- Validated
- Last scraped
- Record created
Additional application data
- Latitude
- 55.389
- Longitude
- -2.8231
What is proposed
Plain-language summary
Proposed 132kV wood-pole overhead power line, around 25km long, linking Millmoor Rig wind farm substation to Hawick substation.
As filed with the council
Installation of 132kV wood pole overheard line, approximately 25km long between Millmoor Rig wind farm substation and Hawick substation