Skip to content

Planning application · SBO/26/00314/SCR

SBO/26/00314/SCRDecidedWorth watching

A 25km overhead line proposed between Millmoor Rig and Hawick.

Millmoor Rig Wind Farm Land South West Of Southdean Lodge Southdean Hawick Scottish Borders

Scottish Borders Council

Preview alerts near this site

Free preview. £1 a month for one alert. Cancel any time.

Preview alerts near your postcode
Category
Telecommunications
Scale
Medium 6/10
Tags
  • Eia Screening
  • Overhead Utility Lines
  • Substation
  • Wind Turbine

Overview

Why it’s worth watching

A 25km high-voltage overhead line is significant energy infrastructure with material landscape and community implications.

Proposed
A 132kV wood-pole overhead line, approximately 25km long
Size
132 kV line voltage · 25 km approximate line length
Stage
Decided: Decided.

The council writes only to properties within 20 metres of an application site. Who is told

Ecu screening opinion - no eia

In plain English

The application is for a wood-pole overhead line between Millmoor Rig wind farm substation and Hawick substation. The line is described as approximately 25km long and rated at 132kV.

Written with AI from the application form and the council record.

Keep reading

Official records · analysis in progress

1,291 of 1,291 official records received 1 Sept 2025 – 31 Aug 2026 were available when checked on 6 Sept 2026.

Proposals and decisions come from Scottish Borders Council. Additional summaries and analysis are being added where verified.

Check the council’s planning register

Track this application

How do I track planning application SBO/26/00314/SCR?

Follow it on City Scope. This page is checked against the Scottish Borders Council planning register and shows the latest status, decision and documents for SBO/26/00314/SCR. City Scope can also email you when a new application is lodged nearby. To comment on the application, use the Scottish Borders Council planning portal.

Set up a planning alert