CityScope · Planning Updates
Application SHE/2024/303/DCON4
600M West Of The Western Extent Of Lerwick BNG HU 44730 42646
Stage 2 Peat Management Plan for Mossy Hill Wind Farm Substation, submitted to discharge Condition 08 covering peat handling and restoration.
The record
- Reference
- SHE/2024/303/DCON4
- Address
- 600M West Of The Western Extent Of Lerwick BNG HU 44730 42646
- Status
- Decided
- Category
- Legal / Administrative
- Impact scale
- 2/10
- Authority
- Shetland Islands Council
Timeline
- Received
- Validated
- Last scraped
- Record created
Additional application data
- Latitude
- 60.166
- Longitude
- -1.2154
What is proposed
Plain-language summary
Stage 2 Peat Management Plan for Mossy Hill Wind Farm Substation, submitted to discharge Condition 08 covering peat handling and restoration.
As filed with the council
Application for consent, agreement or approval required by planning Condition: 08 (Peat Management Plan) of planning application 2024/303/PPF.